There will be several small building alterations completed to our project building during the performance period (vestibule and lobby upgrades, demo and tenant finish build out for entire floor, toilet room upgrades). Can the building flush out occur after all of these alterations are complete? Some will overlap but some will be started after others are complete. However all will occur during 12 month performance period. Thanks!
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
David Posada
Integrated Design & LEED SpecialistSERA Architects
LEEDuser Expert
1980 thumbs up
March 28, 2013 - 4:23 pm
Julie,
It would be better to flush out the altered areas as the work is completed for each area. That way any odors from a floor build-out are mitigated before that space gets occupied, rather than waiting for projects in other parts of the building to be completed.
Julie Pollack
Co-Founder/PrincipalStewart-Pollack Design Associates
2 thumbs up
March 29, 2013 - 1:12 pm
Thanks, David. That makes sense.The Owner's representative is not happy about flushing out the building after every small project but it sounds as if that's the requirement.