EAc6 baseline and PP?EBOM-2009 EAc6: Emissions Reduction Reportingposted by Kasandra Martin on Apr 22, 2016, 5:31 pm
It says there is to be a baseline year to compare with the performance period. My project is an addition to an existing building that has never been certified. So do I need to first have a year... Last reply: Trista Brown, May 2, 2016, 11:38 am |
|
Technical AdviceEBOM-2009 EAc6: Emissions Reduction Reportingposted by Eleftherios Zacharakis on Feb 17, 2016, 4:20 am
Hi, we used ENERGY STAR Portfolio Manager to estimate the CO2 emissions of a project. The review team is requesting we... Last reply: Trista Brown, Apr 23, 2016, 10:12 pm |
|
Emission Reporting (ISO 14064/ Portfolio Manager)EBOM-2009 EAc6: Emissions Reduction Reportingposted by Esteban Martinez on Nov 24, 2015, 9:34 am
Hi, We are working in a project in Colombia. Can we use ISO 14064 certificated (Greenhouse gases) to document... Last reply: Michael Smithing, Nov 24, 2015, 8:03 pm |
|
Transportation emissionsEBOM-2009 EAc6: Emissions Reduction Reportingposted by Gabriel Frasson on Jun 18, 2014, 1:06 pm
Hi Thank you! Last reply: Michael Smithing, Jun 19, 2014, 3:23 am |
|
Statement Of Energy Performance valid for France?EBOM-2009 EAc6: Emissions Reduction Reportingposted by florian Beauchet on Jun 5, 2013, 9:10 am
Hi, I'm a french engineer and I'm wondering if the SEP considers the region of the study. Indeed my site is in France, thus does the... Last reply: Michael Smithing, Nov 8, 2013, 2:31 am |
|
Use of EA Cr 6 for a CS ProjectEBOM-2009 EAc6: Emissions Reduction Reportingposted by emily reese moody on Jun 6, 2013, 1:08 pm
Hi, I'm wondering if anyone has tried attempting this credit as an ID strategy in a CS project. I realize the intent is to show reduction during the performance period of and existing... Last reply: Hannah Bronfman, Nov 7, 2013, 4:20 pm |
|
EAc6 review comment.EBOM-2009 EAc6: Emissions Reduction Reportingposted by Jason Biondi on Jun 15, 2011, 3:41 pm
Has anybody recieved a comment on this credit along the lines of, "provide a summary of actions relating to energy efficiency and emissions reductions estimate the relative contribution of each... Last reply: Jason Franken, Nov 7, 2011, 3:37 pm |
|
Summary Narrative of Actions and CO2 reductionsEBOM-2009 EAc6: Emissions Reduction Reportingposted by Ari Kobb on Nov 6, 2010, 9:02 pm
I was wondering of the narrative must only include efficiency and other actions during the performance period, or can you include "recent" improvements, as well as future improvements identifed... Last reply: Tristan Roberts, Sep 2, 2011, 10:18 am |
|
What happend if the result of SEP on GHG emission is "N/A"EBOM-2009 EAc6: Emissions Reduction Reportingposted by David Feregrino on Jun 16, 2011, 1:37 pm
Hi, I used the EPA's manager Program, and the result for... Last reply: Jenny Carney, Jun 22, 2011, 2:56 pm |
|
PE Stamp on SEPEBOM-2009 EAc6: Emissions Reduction Reportingposted by Carrie Bradley on May 3, 2011, 3:18 pm
EAc1 and EAp2 don't require a PE seal. Is it really required on the SEP submittal for this credit? The guidebook says the SEP "requires confirmation by a validated professional engineer." This... Last reply: Jenny Carney, Jun 22, 2011, 2:54 pm |