Forum » NC-2009 IEQc3.2
Topic

Testing Approach

NC-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by J.R. Anderson on Feb 20, 2013, 6:59 pm

I have a middle school slated to be completed this coming summer.
It will be in late July.
Each classroom has a dedicated ground source heat pump air handling unit. Also, there are...

Last reply: Tristan Roberts, Mar 20, 2013, 7:47 pm

Flushout of Nonoccupied Spaces

NC-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Sally Marr on Feb 12, 2013, 12:16 pm

The 26,000 square foot building that I am working on has several spaces that are not served with supply air by the building's ventilation system, including toilet rooms and mechanical and...

Last reply: Dylan Connelly, Mar 15, 2013, 12:06 pm

Outdoor Air Contamination

NC-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Norma Lehman on Jan 9, 2013, 5:47 pm

We have a project that has failed an...

Last reply: Norma Lehman, Jan 10, 2013, 3:00 pm

Renovation (occupancy never stopped) / 24-hour operation

NC-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Alexandre Schinazi on Dec 5, 2012, 12:27 pm

Hello,

I am working on a project in Brazil with specific conditions that have brought up 2 questions concerning this credit. I'd really appreciate any opinions!

1) It's a major...

Last reply: Dylan Connelly, Dec 5, 2012, 4:56 pm

Continuous flush out?

NC-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Erin Holdenried on Nov 20, 2012, 12:59 pm

For Option 1 Path 2, can there be a time gap between when the pre occupancy ends and post-occupancy flush out begins? Or does one have to immediately follow the other?

Last reply: Dylan Connelly, Nov 29, 2012, 11:10 am

above 60% relative humidity during flush out

NC-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Benjie Herrera on Nov 20, 2012, 4:07 pm

Will a a flush out with above 60% relative humidity be acceptable provided there is a valid reason? The main reason is that further attempt to obtain 60% humidity may affect the complex DDC...

Last reply: Tristan Roberts, Nov 23, 2012, 10:00 am

IAQ Testing method

NC-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Adi Negara, LEED AP BD+C on Jul 25, 2012, 1:00 am

It's clear that for this credit, LEED only accepted...

Last reply: Adi Negara, LEED AP BD+C, Sep 11, 2012, 5:16 am

Can credit 3.2 be earned from a re-test post occupancy?

NC-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Robert Mulcahy on Jun 12, 2012, 4:32 pm

I just completed an...

Last reply: Maura Adams, Jul 3, 2012, 2:29 pm

Timing of IAQ testing compliance

NC-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Anders Olson on Apr 26, 2012, 3:57 pm

I am part of a LEED NC 2009 for Retail project that intends to pursue Option 2 -- Air Quality Testing -- for this credit. The retail requirements differ from the NC requirements in that projects...

Last reply: armando chamorro, May 8, 2012, 4:17 pm

Flushout calcs for Option 1 Path 1

NC-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Mark Haynie on May 7, 2012, 5:52 pm

To achieve the required time needed for flush out, do we only take into consideration the OA louver volume (CFM)? So if we have a total flush volume of 15,000,000 and the OA louver has a CFM...

Last reply: Dylan Connelly, May 8, 2012, 11:47 am