Ductwork Cleaning StandardsNC-2009 IEQc3.1: Construction IAQ management plan - during constructionposted by Candice Rogers on Aug 28, 2012, 9:00 am
My Mechancial Contractor for a project submitted an... Last reply: David Posada, Aug 28, 2012, 12:44 pm |
|
Date and Time Stamped PhotosNC-2009 IEQc3.1: Construction IAQ management plan - during constructionposted by angela cardwell on May 9, 2012, 3:34 pm
The LEEDonline forms request photo documentation with Date and Time stamps. My camera only has the capability for the date stamp but not the time stamp. How stringent will the LEED reviewer be... Last reply: Steve Loppnow, Jun 8, 2012, 5:29 pm |
|
additional covers at return air grillesNC-2009 IEQc3.1: Construction IAQ management plan - during constructionposted by Iris Amdur on May 9, 2012, 3:32 pm
In anticipation for a large dust kick-up during finish installation, our project is looking into placing an additional cloth filter on the return air grilles (in addition to the... Last reply: Susan Walter, May 18, 2012, 10:04 am |
|
HVAC ProtectionNC-2009 IEQc3.1: Construction IAQ management plan - during constructionposted by Patana Rattananavathong on Oct 11, 2011, 4:14 am
I have a project that don't use any HVAC system. It's all natural ventilation. Is it ok to left the HAVC protection out since there is nothing to protect. Can the project apply for this credit... Last reply: Dylan Connelly, Nov 4, 2011, 7:36 pm |
|
Lost IAQ PhotosNC-2009 IEQc3.1: Construction IAQ management plan - during constructionposted by Melissa Wrolstad on Jun 6, 2011, 5:02 pm
I am working on a project with an... Last reply: Allison Beer McKenzie, Jun 6, 2011, 5:21 pm |
|
Direct Exhaust SystemsNC-2009 IEQc3.1: Construction IAQ management plan - during constructionposted by Erik Ruoff on Jul 7, 2010, 9:21 am
Does a project where all exhaust air is exhausted directly to the outside need... Last reply: Tristan Roberts, May 26, 2011, 7:38 am |
|
Moisture ProtectionNC-2009 IEQc3.1: Construction IAQ management plan - during constructionposted by Brad Buser on Mar 3, 2011, 7:01 pm
I need some help understanding the moisture projection requirements of this credit. Our... Last reply: Allison Beer McKenzie, Mar 12, 2011, 11:42 am |
|
Limiting access once the building is enclosedNC-2009 IEQc3.1: Construction IAQ management plan - during constructionposted by Vanessa Seibert on Mar 7, 2011, 12:32 pm
Our experience on projects is that limiting the access to one door with a long, regularly cleaned carpet, is expected by the LEED reviewer. We are currently working on a three story building and... Last reply: Vanessa Seibert, Mar 7, 2011, 5:52 pm |
|
Why does v3.0 form only require photos of moisture damage?NC-2009 IEQc3.1: Construction IAQ management plan - during constructionposted by RETIRED on Jan 19, 2011, 4:26 pm
Hasn't anyone been able to understand why the v3.0 version of the Form for this credit eschews the previous requirements for photographs of... Last reply: Tristan Roberts, Jan 24, 2011, 5:02 pm |
|
Sequencing of Finish MaterialsNC-2009 IEQc3.1: Construction IAQ management plan - during constructionposted by Jennifer Preston on Jan 6, 2011, 10:56 am
Typically carpet needs to be aired out prior to installation, away from any potential sink materials. If the carpet is... Last reply: Allison Beer McKenzie, Jan 6, 2011, 10:59 am |