Forum » NC-2009 EAc2
Topic

Eligibility of PV systems receiving SRECs

NC-2009 EAc2: On-Site Renewable Energy
posted by Adam Prince on Jan 3, 2014, 1:02 pm

I apologize if this was covered explicitly in another discussion. In Massachusetts, there's a well-established SREC market. However, the SRECs are paid whether the electricity is used on site or...

Last reply: Marcus Sheffer, Jan 3, 2014, 3:59 pm

biofuel acquired from utility provider to serve CHP on site

NC-2009 EAc2: On-Site Renewable Energy
posted by Doreen Kruschina on Dec 3, 2013, 10:43 am

Hi,
we are working on a project that will implement a...

Last reply: Marcus Sheffer, Dec 3, 2013, 12:39 pm

PV as a source of energy for ground heat exchange

NC-2009 EAc2: On-Site Renewable Energy
posted by Samuel Sura on Dec 2, 2013, 10:17 am

A project I'm working on is considering a combination of PV and ground source heat pump. The PV will generate approx. 30 kW of energy and this energy will be fed into the heat pump that will use...

Last reply: Marcus Sheffer, Dec 2, 2013, 10:46 am

Renewable energy fraction; with or without process energy?

NC-2009 EAc2: On-Site Renewable Energy
posted by Roberto Oshiro Gama on Nov 12, 2013, 5:00 am

Hi,
I have a question about the...

Last reply: Marcus Sheffer, Nov 12, 2013, 9:42 am

Solar Array on LEED Building- But Not Property of Building

NC-2009 EAc2: On-Site Renewable Energy
posted by Patty Lloyd on Oct 25, 2013, 9:55 am

I was wondering if anyone has had experience with this, and if this scenario can earn LEED points for on-site...

Last reply: Marcus Sheffer, Oct 25, 2013, 12:08 pm

PV energy on campus setting.

NC-2009 EAc2: On-Site Renewable Energy
posted by Muhammad Faisal Azizullah Jaffar on Sep 18, 2013, 3:08 am

I am working on a campus project in Qatar with 3 buildings to be targeted for LEED Gold. 2 of those buildings are close to each other (Cluhouse and Academy). The third building, a training center...

Last reply: Marcus Sheffer, Sep 19, 2013, 9:57 am

On-site Fuel Cells

NC-2009 EAc2: On-Site Renewable Energy
posted by Emilio Rovira on Sep 17, 2013, 1:23 pm

Can we use on-site fuel cells as an ID Credit?

Last reply: Marcus Sheffer, Sep 17, 2013, 3:55 pm

Existing 1MW PV Array feeding new LEED Project on Campus

NC-2009 EAc2: On-Site Renewable Energy
posted by Greg Kight on Aug 22, 2013, 7:51 pm

My project is a LEED v2.2 NC 32,000 sf project going for an 'individual' certification on a campus of existing buildings (None others are certfied or pursuing certification). We are told that...

Last reply: Greg Kight, Aug 23, 2013, 3:40 pm

Bio-fuel Boilers

NC-2009 EAc2: On-Site Renewable Energy
posted by Martin Meehan on Nov 8, 2011, 6:36 am

From my reading of the Reference Manual for this credit it seems that Bio-fuel can only be used to generate electrical power on-site, and not to power bio-fuel boilers for water heating or space...

Last reply: Joern Drosten, Aug 21, 2013, 11:01 am

Biomass Qualifications

NC-2009 EAc2: On-Site Renewable Energy
posted by Anthony Schoen on Jul 9, 2013, 4:38 pm

We are currently starting a project that utilizes a biomass central steam plant. This plant uses...

Last reply: Marcus Sheffer, Jul 10, 2013, 9:30 am