SIGNALIZATION SIZE

CS-2009 SSc4.3:Alternative Transportation—Low-Emitting and Fuel-Efficient Vehicles
posted by  OSCAR DE LA RED  on 

Is there any requirement for the signalization size and position (on the wall, on the floor, etc..) for credit 4.3 preferred parking places?

2
Tue Feb 16, 2016, 7:29 pm

Case 1 - Grouping the space types

EBOM-2009 IEQp1:Minimum IAQ Performance
posted by  satheesh M  on 

Hi, we are working for the project with multiple tenants. we could not collect all the floors HVAC layouts. but we have the AHU details.

4
Practice Leader - Sustainability
EUA
LEEDuser Expert
510 thumbs up
Tue Feb 16, 2016, 6:34 pm

Existing Building Baseline WWR

NC-2009 EAc1:Optimize Energy Performance
posted by  Christian Kaltreider  on 

Referencing 90.1 Table G3.1.5: I understand that the envelope for an existing building baseline model should reflect existing conditions concerning thermal properties of walls and windows.

4
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Tue Feb 16, 2016, 5:58 pm

Applicable credits for chemical free cooling tower maintenance

EBOM-2009 WEc4:Cooling Tower Water Management
posted by  Julie Klein  on 

I am looking at a chemical free cooling tower maintenance system that returns huge water savings. Is there a threshold on the number of credits for one facility component?

4
Founder & Community Director
Metricorps
LEEDuser Expert
7780 thumbs up
Tue Feb 16, 2016, 5:30 pm

Dormitory Project- Single Bedrooms like Private Offices

NC-2009 IEQc8.2:Daylight and Views—Views
posted by  Emma Leonard  on 

I am working on a dormitory project with mainly single bedrooms. Can I count these rooms like private offices and not have to calculate the actual area in each space?

2
Energy Program Specialist
PA DMVA
LEEDuser Expert
626 thumbs up
Tue Feb 16, 2016, 3:00 pm

Linen Area

Healthcare-v2009 IEQp1:Minimum indoor air quality performance
posted by  Gabriela Crespo  on 

Hi! I have a question regarding the ventilation requirement for the Linen Area, according to the Space Matrix file, there needs to be Outdoor air for this space.

2
LEED-AP BD+C
GREENSQUARE
LEEDuser Expert
261 thumbs up
Mon Feb 15, 2016, 3:38 pm

Outside Mat

NC-2009 IEQc4.3:Low-Emitting Materials—Flooring Systems
posted by  Waterset CDD  on 

Hello, We have an outside mat that needs to be replaced. It was actually glued down during instillation. I would like to know the following: 1.

2
Founder & Community Director
Metricorps
LEEDuser Expert
7780 thumbs up
Fri Feb 12, 2016, 5:31 pm

Museum Exhibit Lighting

NC-2009 EAc1:Optimize Energy Performance
posted by  Christian Kaltreider  on 

I am modeling a museum with separately controlled exhibit lighting. I am using Section 9.6 of 90.1 2007 (space by space) to calculate my baseline general lighting power densities.

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Thu Feb 11, 2016, 9:54 pm

Waste Oil Fuel

NC-2009 EAp2:Minimum Energy Performance
posted by  Michael Daly  on 

I am working on a project that has two parts to the building. There is an office component and a shop component. The office is going to be heated and cooled with a VRF system.

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Thu Feb 11, 2016, 9:49 pm

Perimeter protection

NC-2009 SSp1:Construction Activity Pollution Prevention
posted by  Martin Meehan  on 

We have a number of LEED projects in infill locations in Ireland. Since we don't really have a standard code for site Erosion and Sedimentation we have to stick to the U.S.

3
Default Avatar
Principal
Meehan Associates
LEEDuser Basic Member
14 thumbs up
Thu Feb 11, 2016, 6:22 pm