Have any project teams had success using two different commissioning agents from two different entities in order to perform commissioning services on their project? For example, can the
Diverted vs Commingled in LEED Online Form
NC-2009 MRc2:Construction Waste Managementposted by Dionisio Franca on
Hello!
The LEED Online Form has three option under Disposal Method: Commingled, Diverted, Landfill Waste. By choosing "commingled", you can input the percentage diverted.
Treatment Requirements
NC-v4 SSc4:Rainwater managementposted by Annie Levan on
Hello,
Can someone please clarify the treatment requirements for various storm water strategies? A few example strategies are as followed:
Building eyebrows count towards area?
NC-2009 SSc7.2:Heat Island Effect—Roofposted by Nicole Kimoto on
We have a project where we have concrete eyebrows protruding from the building exterior. Would the area of those eyebrows count towards roof area?
Percent of Occupants
NC-v4 WEp2:Indoor water use reductionposted by Amy Ruffino on
On the Reduction Calculation spreadsheet, how should the "Percent of Occupants" be filled out for kitchen sinks or urinals?
And/or Options?
EBOM-v4 SSc1:Site Development- protect or restore habitatposted by Branka Zivkovic on
Hello,
Reference Guide says in Requirements that that it is Option 1 (On-site restoration) OR Option 2 (Financial support).
Construction Waste on a phased project
NC-2009 MRc2:Construction Waste Managementposted by Faith Wilbert on
I was brought on to help finalize templates for a LEED submission. The project was started with Phase 1 - 7 years ago. Phase 1 was Site and Foundations.
HVAC Baseline System 8 - with Purchased Chilled Water only
NC-v4 EAp2:Minimum energy performanceposted by Amgad Khattab on
We are working on a project where the selected baseline HVAC system type is 8 with purchased chilled water only from a district cooling plant.