Do kitchen make-up air fans require outdoor airflow monitoring devices? (For non-densely occupied spaces)
NC-2009 IEQc1:Outdoor Air Delivery Monitoringposted by Jane Lane on
We have two KSFs serving two separate kitchen hoods.
OEKO-TEX Standard 100: Conforms with LEED?
CI-v4 EQc2:Low emitting materialsposted by Kena David on
We are evaluating a fabric wall covering. The only testing documentation we can find is OEKO-TEX Standard 100 (Class II).
Project Commercial Interior in existing building.
CI-v4 EAc2:Optimize energy performanceposted by Vassil Vassilev on
The issues is related to the cooling.
Greetings,
Bike spaces usage
NC-2009 SSc4.2:Alternative Transportation—Bicycle Storage and Changing Roomsposted by Karyn Rodrigues on
Hello! I have a LEED NC project that is already operating and we are now finishing DR+CR submittals.
Sufficient alternative-fuel stations need to be provided to comply with SSc4.3, Option 2
NC-2009 SSc4.3:Alternative Transportation—Low-Emitting and Fuel-Efficient Vehiclesposted by Hanh Truong on
We are pursuing in this credit the "Option 2: Providing onsite alternative fueling stations for 3% of total vehicle parking capacity"
LEED and Elevators
NC-v4 EAp2:Minimum energy performanceposted by erica colleoni on
Hello everyone,
Off-site PV farm financed by property owner
EBOM-2009 EAc4:On-Site and Off-Site Renewable Energyposted by Dricka Brown Thobois on
I am working with a property who is going for LEED EBOM recertification. The property is owned by a large business that has financed, owns, and maintains, a very large PV farm on the wes
Not enough finishes to meet credit.
NC-v4 MRc2:Building product disclosure and optimization - environmental product declarationsposted by Max Krueger on
Hi,
I have a small building with less than 20 finishes. I presume this means the credit cannot be met?
Thanks,
Max
Clarification for Calculations to be provided
Pilot-Credits MRpc87:Verified Construction & Demolition Recycling Ratesposted by Kristen Magnuson on
One of the requested items to document compliance with this credit is the following:
Motorcycle Parking space
NC-v4 SSc5:Heat island reductionposted by Floyd Valade on
Is motorcycle parking (still) included in the total parking calculation, for V4, SSC5-Heat Island Effect Credit-OP-2,Parking Under Cover? Thnx in adv.