Forum quick links
Roll-out mats details
CS-2009 IEQc5:Indoor Chemical and Pollutant Source Controlposted by Summer on
Anyone can confirm if all roll-out mats should be provided with zocallo to insert the carpet?
Roll-out mats for entrance only and exit not included
CS-2009 IEQc5:Indoor Chemical and Pollutant Source Controlposted by Summer on
Hello everyone,
Airport Terminal Building - Rating System Adaption
posted by Konstantina Kalliakoudi on
Hello to all,
Animal Research Facility with attached gates
EBOM-2009 MRc9:Solid Waste Management—Facility Alterations and Additionsposted by Amy Burns on
We are a higher education campus and are Facility Alteration that had attached gates that were used for the animal research but are not needed now.
VOC budget process in this credit
NC-2009 IEQc4.3:Low-Emitting Materials—Flooring Systemsposted by Albert Sagrera on
Can I use the same "VOC budget process" to justify this credit as in credit 4.2 if I make a misatke or If I have just one product that is used minimally on a project?. Thanks
Certification required to perform pressure differential test?
NC-2009 IEQp2:Environmental Tobacco Smoke (ETS) Controlposted by Vanessa Nelson on
Is a certification required to perform the pressure differential test? I'm wondering if it needs to be done by a specialty testing company or can it be done by the Mechanical Sub?
Documents - which Language?
posted by Ernst Schriefl on
Hi,
This is maybe an obvious question but our projects are located in Austria. Therefore most of our documents are in German.
Single Phase UPS
CI-2009 EAc1.4:Optimize Energy Performance—Equipment and Appliancesposted by Omar Delgado on
Greetings all, I have a CI project that has single phase UPS, PoE Switches, and some AiroNet AP. Are all these excluded from the calculation? Thanks!
calculating rated power and bigger questions
CI-2009 EAc1.4:Optimize Energy Performance—Equipment and Appliancesposted by Michele Helou on
I cannot get the nameplate power from an Energy Star residential refrigerator used for a commercial project. I called the manufacturer, checked the manuals, etc. no luck.
More on UPS s
CI-2009 EAc1.4:Optimize Energy Performance—Equipment and Appliancesposted by Susan Di Giulio on
Hi, I understand all the previous discussion UPSs but our situation is just a tad different, The project in question is intensely tech related, and the UPS needed as backup is a 3 phase, 50,000 kV