Topic | Recent |
---|---|
No Cooling TowerNC-v4.1 WEc3: Optimize Process Water Useposted by Azra Semic on Jun 14, 2023, 8:10 am
Hello, we are working on numerous projects which do not include a cooling tower nor evaporative condensers. Last reply: Dave Hubka, Jul 24, 2023, 6:05 pm |
|
"No cooling tower" option removedNC-v4.1 WEc3: Optimize Process Water Useposted by Paula Melton on Dec 2, 2020, 9:39 am
It appears that Option 2, "No Cooling Tower," has been removed from this credit with addendum #10002465. Last reply: Azra Semic, Jun 14, 2023, 6:24 am |
|
Option 1- what is the minimum number of cyclesNC-v4.1 WEc3: Optimize Process Water Useposted by Gustavo De las Heras Izquierdo on Nov 30, 2022, 3:08 pm
Hello, Let's say that my project has a bad quality of potable water, and the concentration levels are the same as Table 2. Therefore, the maximum number of cycles would be "1 cycle". ... |
|
Option 1- what is the maximum number of cyclesNC-v4.1 WEc3: Optimize Process Water Useposted by Michael on Jun 27, 2022, 11:38 am
The guideline said to maximize the number of cycles by not exceeding the maximum concentration level. However, it's unclear what is the maximum cycle numbers that LEED is looking for. In LEED v4... Last reply: Maeve Donohue, Jun 28, 2022, 12:53 pm |
|
Defining baseline water consumption for Optimize Process Water Use Option 2NC-v4.1 WEc3: Optimize Process Water Useposted by Oliver Pearce on Jun 1, 2022, 2:29 am
Hi, We are investigating the potential to demonstrate that the cooling solution in our project is more water efficient than a baseline according to LEEDv4.1 Optimize... |
|
Optimize Process Water Use, Option 2 with ASHRAE 90.1 2010 model?NC-v4.1 WEc3: Optimize Process Water Useposted by Deb Favaretto on Nov 9, 2021, 2:37 pm
We are submitting a LEED v4 BD+C NC project with LEED v4.1 upgrades on a credit-by-credit basis. Minimum and Optimize Energy Performance have remained v4. We are interested in pursuing the v4.1... Last reply: Afogreen Build, Feb 15, 2022, 1:00 am |
|
Process water use- total building regulated water use definitionNC-v4.1 WEc3: Optimize Process Water Useposted by Zsuzsanna Gidro on Sep 28, 2021, 10:01 am
Hi! It is unclear to me what does the total building regulated water use means in this case. Is this equal to the indoor water use (plumbing fixtures use) calculated in the prerequisite?... |
|
Chlorine as a biocide treatmentNC-v4.1 WEc3: Optimize Process Water Useposted by Ricardo Sá on Feb 15, 2021, 4:49 am
Dear All |
|
The project is the central energy plantNC-v4.1 WEc3: Optimize Process Water Useposted by Stephanie Graham on Jul 17, 2020, 11:16 am
Our project is a LEED v4/v4.1BD+C new central cooling plant which uses geothermal for cooling on a university campus. Besides the plant, the building has office areas for the operators of the... |
|
Is residential project are not eligible for Option 2?NC-v4.1 WEc3: Optimize Process Water Useposted by Leanne Niu on Jun 5, 2020, 2:56 am
we have a residential project with no cooling tower, if it is eligible for Option 2? |