MRpc103- Integrative Analysis of Building MaterialsPilot-Credits MRpc103: Integrative Analysis of Building Materialsposted by Mario Kranzl on Aug 2, 2023, 7:40 am
We were at the begining quite overwhelmed with this one. It seemed like a complicated thing to do, since the analysis went really much deeper than any of the other credit required it to. But we... Last reply: Maegan Sweeney, Jan 12, 2024, 9:38 am |
|
No Cooling TowerNC-v4.1 WEc3: Optimize Process Water Useposted by Azra on Jun 14, 2023, 8:10 am"Option 2. Optimize Water Use for Cooling" if they meet the eligibility criteria described in the Step-by-Step Guidance. In another forum on this matter titled "No Cooling Tower option... Last reply: Brittany Garneau, Dec 19, 2023, 8:21 am |
|
what's the definition of occupants for Hospitality?EBOM-v4 LTc1: Alternative Transportationposted by Ernst Schriefl on Dec 14, 2023, 10:15 am
what's the definition of occupants for Hospitality? Which identity groups belongs to occupants of Hospitality and should be surveyed? |
|
Parking Lots at undergraound at the basementNC-v4 LTc7: Reduced parking footprintposted by Stephan Zweig on Oct 5, 2022, 4:33 am
Hello, I have following question: If in a project there are parking lots in the building at the basement, can this project be eligible for the credit “reduced parking”? ... Last reply: J Schütz, Oct 7, 2022, 5:19 am |
|
BD+C MAJOR RENOVATION- How is mahor renovation defined?LEED Rating System Selectionposted by Stephan Zweig on Oct 5, 2022, 4:29 am
Hello, For rating system BD+C Major Renovation: How is Major Renovation Defined? Is there a proving document required to upload to state that the existing building is under MAJOR... |
|
OPR and BOD docunetsLEED Reviews: Appeals, Design/Construction Submittals, and moreposted by Stephan Zweig on Oct 5, 2022, 4:13 am
Hello, at the LEED on line platform for the LEED Documentation do we need to upload the documents Owners Project Requirements (... |
|
Time Frame for LEED Precertification and/or Deadline to submit narratives after Preliminary Review!LEED Reviews: Appeals, Design/Construction Submittals, and moreposted by Amjad Ali H Ahmadalshteihi on Oct 3, 2022, 3:37 am
Deal LEED fellows, we have receivedPrecertification Preliminary Review on 19.09.2022 from LEED and some credits are not rewarded with any points and states beside it that it is still... |
|
validity of LEED certificate (LEED-CS v2009); necessary period of USGBC membershipPerformance Periodposted by Ernst Schriefl on Oct 1, 2018, 6:42 am
We are in the process of certifying several buildings under a campus approach (LEED Master Site D+C), where each building / project is certified unter the LEED-CS v2009 rating system. The... Last reply: Trista Brown, Aug 10, 2022, 11:29 am |
|
Comparison between the three systems BREEAM, DNGB LEEDLEED Rating System Selectionposted by Wisam Maddni on Mar 9, 2022, 4:03 am
Dear ladies and gentlemen, I would like to ask this question: Are there currently properties that have several certification systems (... |
|
Fog Installation on the rooftopNC-v4 WEc1: Outdoor water use reductionposted by Christoph Keck on Jan 25, 2022, 6:37 am