Topic | Recent |
---|---|
IAQ testingSchools-2009 IEQc3.2: Construction IAQ management plan - before occupancyposted by Danielle Dunn on Nov 7, 2018, 1:51 pm
"One test is required for each separate ventilation system within the building, with not less than one sample per 25,000 ft2 of contiguous floor area." Is this statement... |
|
Post construction AND Post Occupancy Flush OutSchools-2009 IEQc3.2: Construction IAQ management plan - before occupancyposted by Denise Domino on Jul 14, 2017, 11:02 am
3.2... Last reply: Tristan Roberts, Aug 26, 2017, 8:09 pm |
|
IAQ Management Plan- Post construction measuresSchools-2009 IEQc3.2: Construction IAQ management plan - before occupancyposted by Maya Karkour on Oct 31, 2011, 4:37 am
Dear all, The LEEDOnline letter template for IEQc3.2 includes a portal to upload the... Last reply: Denise Domino, Jul 13, 2017, 9:45 am |
|
Flush out and un-touched area in LEED boundarySchools-2009 IEQc3.2: Construction IAQ management plan - before occupancyposted by Todd Bundren on Feb 11, 2013, 11:56 am
My project includes the renovation of an existing building and a major attached addition (over 70% of the project is new construction). The existing building has an existing gymnasium (this is a... Last reply: Tristan Roberts, Nov 4, 2013, 8:34 pm |
|
2 options, Flush out and Air testingSchools-2009 IEQc3.2: Construction IAQ management plan - before occupancyposted by Yazmin Trueba on May 7, 2013, 5:08 pm
230k School, Tight Schedule, Path 1 Flushout before occupancy, Per Phases, 21 Air Handler Units / Zones, 6 areas of Flushout durations from 99 days to 30 days. Last reply: Tristan Roberts, Nov 4, 2013, 8:33 pm |
|
How to conduct a flush out during a phased construction projectSchools-2009 IEQc3.2: Construction IAQ management plan - before occupancyposted by Cheryl Burkinshaw on Jul 9, 2012, 3:41 pm
We are working on a renovation project where construction is being conducted in phases. The first phase will be occupied with temporary floor finishes in some spaces prior to final install of... Last reply: Dylan Connelly, Aug 3, 2012, 4:26 pm |
|
measuring and reporting temperature & RHSchools-2009 IEQc3.2: Construction IAQ management plan - before occupancyposted by Eri Spaulding on May 2, 2012, 10:37 am
Does anybody know how to measure and report indoor temperatures and relative humidity during flushout? Do we need to record min. and max. every single day at every single room? or can we just... Last reply: Dylan Connelly, May 2, 2012, 4:25 pm |
|
Flush Out in StagesSchools-2009 IEQc3.2: Construction IAQ management plan - before occupancyposted by Nell Achtmeyer on Mar 7, 2012, 6:35 pm
I am wondering if it's possible to sequence the flush out in stages so that you can make your way through the building, but also maintain work in other parts as well... Last reply: Dylan Connelly, Mar 16, 2012, 12:58 pm |
|
Monitoring Humidity?Schools-2009 IEQc3.2: Construction IAQ management plan - before occupancyposted by Ara Massey on Jun 23, 2011, 7:04 pm
I am currently working on a project in southern Colorado (very dry) that is doing a phased flush-out but there is currently no way to monitor interior humidity. Would a narrative describing that... Last reply: Tristan Roberts, Nov 16, 2011, 11:30 pm |
|
IAQ Testing and FurnishingsSchools-2009 IEQc3.2: Construction IAQ management plan - before occupancyposted by Q + on Mar 21, 2011, 5:28 pm
The Credit Language contains this statement regarding air quality testing and furnishings: "Movable furnishings such as workstations and partitions should be in place for the testing, although... Last reply: Tristan Roberts, Mar 29, 2011, 12:38 am |