who has to pay for the renewable systems?

CS-2009 EAc2: On-Site Renewable Energy
posted by Tatjana Ernst on Nov 24, 2010, 5:48 am

Hi Everyone,

we have an Core&Shell office Building. The Owner is not providing any...

Last reply: Marcus Sheffer, Sep 7, 2018, 10:56 am

Onsite Renewable for 1% of owner controlled annual energy cost.

CS-2009 EAc2: On-Site Renewable Energy
posted by Dave Hubka on Nov 10, 2016, 2:07 pm

Hi Marcus,

I've recently been asked if we could prorate the "1% renewable" to account for only the owner controlled annual energy consumption cost rather than the total building annual...

Last reply: Marcus Sheffer, Nov 10, 2016, 2:44 pm

Calculation method

CS-2009 EAc2: On-Site Renewable Energy
posted by Ciaran McCabe on Jan 28, 2016, 10:36 am

Hi to target this credit for a new project do you need an energy model to predict what 1% energy cost of is there an alternative approach ? We currently don't have an energy model for this...

Last reply: Marcus Sheffer, Jan 29, 2016, 9:46 am

Heat Recovery Counts?

CS-2009 EAc2: On-Site Renewable Energy
posted by Dina Ammar on Jul 28, 2015, 10:29 am

Hello,

Will the energy harvested from a heat recovery equipment installed on a chiller and/or the fresh air system in our project count towards on-site...

Last reply: Marcus Sheffer, Jul 28, 2015, 10:40 am

Help w/ wrangling RECs.

CS-2009 EAc2: On-Site Renewable Energy
posted by Brian Salazar on May 19, 2015, 4:13 pm

Preface: LEED CS v3.0 Project in Massachusetts.

Our project is designed to produce 16% on-site...

Last reply: Marcus Sheffer, Jul 9, 2015, 5:05 pm

Is EAc2 affected by the use of the ACP calculation for EAc1?

CS-2009 EAc2: On-Site Renewable Energy
posted by Charlie Christenson on Mar 25, 2015, 6:32 pm

Working on a core & shell project that is planning to install a PV system sized to offset 1% of total building energy cost. Per the ACP calculation for EAc1, this 1% will be derated by the...

Last reply: Marcus Sheffer, Mar 26, 2015, 3:05 pm

Feed-in Tariff Program Allowed?

CS-2009 EAc2: On-Site Renewable Energy
posted by Laura Billings on Apr 26, 2014, 6:14 pm

I'm representing a building owner/Landlord who is building a new multi-tenant office building and planning a very large solar installation, targeting net zero electricity and LEED-CS Platinum....

Last reply: Marcus Sheffer, Apr 28, 2014, 10:33 am

Reference for the building annual energy cost

CS-2009 EAc2: On-Site Renewable Energy
posted by Ricardo Sá on Sep 7, 2012, 10:11 am

In a Core&Shell project, the percentage of...

Last reply: Maya Karkour, Mar 24, 2014, 1:02 pm

PV System as part of a Master Site

CS-2009 EAc2: On-Site Renewable Energy
posted by Ben Tucker on Oct 15, 2013, 10:03 am

Does anyone have any experience submitting for EAc2 as part of a Master Site? Our project is a campus project that will contain three buildings. The first is complete, the second is under...

Last reply: Ben Tucker, Oct 15, 2013, 4:48 pm

Different commencements of green power contract and biogas CHP

CS-2009 EAc2: On-Site Renewable Energy
posted by Joern Drosten on Aug 8, 2013, 10:43 am

Dear all,

our project will get a biogas...

Last reply: Marcus Sheffer, Aug 12, 2013, 9:45 am