Forum » CS-2009 PIf1
Topic

Change Certification level after Preliminary Design & Construction review

CS-2009 PIf1: Minimum Program Requirements
posted by Ronnel Flores on May 8, 2020, 5:01 am

Is it allowable that for Preliminary Design & Construction (D&C) submission, the project attempt for example, Silver rating. But after preliminary D&C review/comment, and preparing...

Last reply: Ronnel Flores, May 15, 2020, 1:31 am

Confirmation of Agent's Authority

CS-2009 PIf1: Minimum Program Requirements
posted by Mary Guest on Apr 16, 2019, 4:20 pm

Hello! In a LEED Core project and when there is a property management company that represents the owner, how is that communicated on the Confirmation of Agent's Authority form?   If the...

Apply for extension to submission deadline

CS-2009 PIf1: Minimum Program Requirements
posted by Mary Guest on Mar 28, 2019, 1:23 pm

Hi! I was wondering if anyone had experience with submitting a project for review after the deadline of 2 years past of certificate of occupancy.  The team here was not aware of that deadline, so...

please post to a SPECIFIC LEEDuser forum

CS-2009 PIf1: Minimum Program Requirements
posted by Tristan Roberts on Dec 30, 2015, 12:41 pm

Hi. This LEEDuser forum is specifically about completing the PI form 1. Most people's questions here are about either policy compliance with MPRs, or about the review process. Please post your...

Multiple Buildings Project Certification

CS-2009 PIf1: Minimum Program Requirements
posted by Mario S. on Jun 17, 2015, 7:38 am

We have a project with 3 buildings located on the same plot, that are physically attached by two underground levels made up of technical rooms, parking spaces, bicycle racks, showers and garbage...

Energy Star's Portfolio Manager Tool

CS-2009 PIf1: Minimum Program Requirements
posted by Kathryn Van Nelson on Jun 11, 2014, 4:48 pm

Who exactly registers a project with Energy Star's Portfolio Manager Tool?

Last reply: Susan Walter, Jan 19, 2015, 2:19 pm

Additional Floors for Existing LEED Certified Project

CS-2009 PIf1: Minimum Program Requirements
posted by Nandana Kumar on Jan 19, 2015, 5:28 am

Hi
We have a project which is G+10 floors & is LEED CS 2008 Gold certified. Now the developer is planning to expand this building by adding 4 more floors over and above the 10th floor....

LEED baundary

CS-2009 PIf1: Minimum Program Requirements
posted by gabriel Morales on Mar 26, 2014, 4:50 pm

gabriel Morales Architect Kmbio LEEDuser Basic Member 25 thumbs up April 3, 2014- 11:07 am Please it is important to have the support. You have any suggestions? Log in or register to post comments Tristan Roberts Representative Vermont House of Representatives LEEDuser Expert 11473 thumbs up April 3, 2014- 1:23 pm Gabriel, please post this question to our MPR3 forum, while also reviewing the guidance and forum discussions on that page. I'll follow up there. Log in or register to post comments gabriel Morales Architect Kmbio LEEDuser Basic Member 25 thumbs up April 3, 2014- 5:42 pm Thanks tristan Log...

Last reply: gabriel Morales, Apr 3, 2014, 5:42 pm

Single Family Residential Villa 4500 Sqm (G+1),

CS-2009 PIf1: Minimum Program Requirements
posted by Mohd Imran Shaikh on Mar 10, 2014, 4:41 am

Hi There,

Clients wants to attain LEED for Silver Certification for its Villa. Note that the Villa is 4500 sqm and meets the minimum floor area requirement. The project will be carried...

Last reply: Mohd Imran Shaikh, Mar 11, 2014, 8:18 am

LEED V3 or V4 for LEED CS project

CS-2009 PIf1: Minimum Program Requirements
posted by Jin Yang on Mar 1, 2014, 11:52 am

Hi Kemberly,
I'm planning to register a LEED CS project in China that needs precertification as soon as possible. The project was assessed under LEED V3 when the owner decided to pursue...

Last reply: Tristan Roberts, Mar 10, 2014, 9:52 am