Is it allowable that for Preliminary Design & Construction (D&C) submission, the project attempt for example, Silver rating. But after preliminary D&C review/comment, and preparing for Final D&C submission, we change our target Certification level either higher (Gold) or lower (Certified)?
Thank you!
Summer Minchew
Managing PartnerEcoimpact Consulting
LEEDuser Expert
170 thumbs up
May 8, 2020 - 7:23 am
Yes this happens quite frequently.
Ronnel Flores
EcoSolutions1 thumbs up
May 15, 2020 - 1:31 am
Thank you, Summer. Moreover, i hope this understanding as correct: it will then be the reviewer's decision if they award us say, Silver or Gold depending on the extent of completeness of our submitted documents for Final D&C.
Thank you.