Air Testing before Occupancy for phased move-in
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Karl Heitman on
How does LEED interpret occupancy date?
IAQ Testing
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Kelly Searle on
I am working on a major renovation project - 11 story office building.
Is 4,300 = 4,500?
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Lewis Hewton on
Has anybody else noticed the LEED submission form for IEQc3.2 converts 14,000 cf/sf to 4,500m3/m2.
Area not in scope of project
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Carl Rappa on
We have a renovation & addition project where the CM wants to do the Option 2: Air Testing to achieve IEQc3.2.
IEQ 3.2 NC-V2009
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Peter Del Sette, Jr on
IAQ testing in a new addition
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Shawn Keith on
We have chosen to perform IAQ testing on a new additon we are building onto an existing building.
IAQ testing in a new addition
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Shawn Keith on
We are have chosen to perform IAQ testing on a new additon, to a we are building.
Testing Approach
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by J.R. Anderson on
I have a middle school slated to be completed this coming summer. It will be in late July. Each classroom has a dedicated ground source heat pump air handling unit.
Definition of 'occupancy'
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by MT A on
We are planning to pursue this credit and would like to better understand if occupancy is tied to 'substantial completion' occupancy or is occupancy understood as a more high level idea - when the
flush out possible by phase
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Sahar Abi-Ziki on
Hello the first phase (parking garage) of our project will be delivered to client for occupancy now, but the rest of the project will still be under construction for a while.