Is there any guideline to the sampling criteria such as the measurement interval during the normal occupied hours? In Hong Kong the sampling period required by Env. Dept is on 8-hour basis with an average of half-hour measurements conducted at 4 time-slots. I wonder if this can fulfill the criteria of LEED. Thanks!
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Allison Beer McKenzie
Architect, Director of SustainabilitySHP Leading Design
LEEDuser Expert
646 thumbs up
July 22, 2010 - 8:13 am
For LEED, samples only need to be taken at one time, but the must be taken during normal occupied hours with the HVAC system starting at normal daily start times and operating at the minimum outside airflow rate.