In-house CxA with In-house Design, MEP, and Construction Teams
NC-2009 EAc3:Enhanced Commissioningposted by Simon Sue on
We're under a scenario that a developer (owner) has in-house design team, in-house MEP team, and in-house construction team working on a single project.
Retro-Enhanced Commissioning
NC-2009 EAc3:Enhanced Commissioningposted by Christian Pegher on
Our project is on hold until the fall. The construction documents are done, and the owner just hired a CxA. They'd like to have the CxA go back through the documents now and provide feedback.
CxA
NC-2009 EAc3:Enhanced Commissioningposted by Jamal Uddin on
If the task of CxA complete in design phase now for my building but the building construction will be finished totally after 4/5 years from now.
Not all systems are implemented by the time of occupancy
NC-2009 EAc3:Enhanced Commissioningposted by Magda Aghababyan on
Dear all, Can you please advise me on a situation where the design states part of the building to be conditioned and the other part is ventilated but by the time occupancy happens the owner has de
Commissioning Starting After 50% CDs
NC-2009 EAc3:Enhanced Commissioningposted by Sara Zoumbaris on
I could have sworn there was an LI (LEED Interpretation) discussing / approving a certain scenario where Enhanced Commissioning had been started after 50% CDs and was still acceptable under this cr
Can an employee from contruction management firm be CxA
NC-2009 EAc3:Enhanced Commissioningposted by Panupant Phapant on
Hi According to the EAp1 Fundamental Commissioning and EAc3 Enhanced Commissioning' s requirements regarding the qualifications of the CxA as follows: - EAp1: The invidual serving as the CxA
Enhance commissioning
NC-2009 EAc3:Enhanced Commissioningposted by Mamdooh Amin on
Do we have to include the contract document between the owner and the CxA?
Commissioning firm instead of a specific person?
NC-2009 EAc3:Enhanced Commissioningposted by Veronika Sundberg on
Since our project is quit big we have hired an independent firm for our commissioning of the project and not a single person.
Can the CxA be involved in the thermal model of EAp2?
NC-2009 EAc3:Enhanced Commissioningposted by Maya Karkour on
Dear All, We are consulting for a large LEED-NC tower. The thermal model for EAp2 / EAc1 were undertaken by a company independant from the design team.