In-house CxA with In-house Design, MEP, and Construction Teams

NC-2009 EAc3:Enhanced Commissioning
posted by  Simon Sue  on 

We're under a scenario that a developer (owner) has in-house design team, in-house MEP team, and in-house construction team working on a single project.

1
Wed Dec 5, 2012, 1:26 pm

Retro-Enhanced Commissioning

NC-2009 EAc3:Enhanced Commissioning
posted by  Christian Pegher  on 

Our project is on hold until the fall. The construction documents are done, and the owner just hired a CxA. They'd like to have the CxA go back through the documents now and provide feedback.

1
Sat Aug 5, 2017, 5:08 pm

CxA

NC-2009 EAc3:Enhanced Commissioning
posted by  Jamal Uddin  on 

If the task of CxA complete in design phase now for my building but the building construction will be finished totally after 4/5 years from now.

1
Wed Jul 17, 2013, 3:09 pm

Not all systems are implemented by the time of occupancy

NC-2009 EAc3:Enhanced Commissioning
posted by  Magda Aghababyan  on 

Dear all, Can you please advise me on a situation where the design states part of the building to be conditioned and the other part is ventilated but by the time occupancy happens the owner has de

1
Tue Mar 25, 2014, 8:03 pm

Commissioning Starting After 50% CDs

NC-2009 EAc3:Enhanced Commissioning
posted by  Sara Zoumbaris  on 

I could have sworn there was an LI (LEED Interpretation) discussing / approving a certain scenario where Enhanced Commissioning had been started after 50% CDs and was still acceptable under this cr

1
Mon Nov 2, 2015, 10:03 pm

Can an employee from contruction management firm be CxA

NC-2009 EAc3:Enhanced Commissioning
posted by  Panupant Phapant  on 

Hi According to the EAp1 Fundamental Commissioning and EAc3 Enhanced Commissioning' s requirements regarding the qualifications of the CxA as follows: - EAp1: The invidual serving as the CxA

1
Wed Aug 28, 2013, 4:50 pm

Enhance commissioning

NC-2009 EAc3:Enhanced Commissioning
posted by  Mamdooh Amin  on 

Do we have to include the contract document between the owner and the CxA?

1
Tue Aug 9, 2016, 3:07 pm
1
Tue Jul 27, 2010, 6:54 pm

Commissioning firm instead of a specific person?

NC-2009 EAc3:Enhanced Commissioning
posted by  Veronika Sundberg  on 

Since our project is quit big we have hired an independent firm for our commissioning of the project and not a single person.

1
Fri Feb 10, 2012, 1:41 pm

Can the CxA be involved in the thermal model of EAp2?

NC-2009 EAc3:Enhanced Commissioning
posted by  Maya Karkour  on 

Dear All, We are consulting for a large LEED-NC tower. The thermal model for EAp2 / EAc1 were undertaken by a company independant from the design team.

1
Mon Dec 3, 2012, 7:43 pm