NC-2009 EAc3:Enhanced Commissioningposted by Chris Flint Chatto on
We are working on a design-build team developing a project that will be leased to a government agency.
Enhanced Cx - EAc3;
NC-2009 EAc3:Enhanced Commissioningposted by Miles Britz on
Systems Manual; on our Const. Phase submittal the reviewer stated we need to include a Systems Manual. It appears this refers to the Training of staff on the bldg.'s.
10-Month Review
NC-2009 EAc3:Enhanced Commissioningposted by Peter Dishno on
Does anyone have any advice on doing 10-Month Reviews? A past company I have worked at did a sample re-commissioning of the systems.
Who Can Be the Commissioning Authority
NC-2009 EAc3:Enhanced Commissioningposted by Robin Dukelow on
Hello, I am trying to locate the full document but only have been able to find the Table that was published. Does anyone know where I can find this information? - Thank you!
CxA also testing and balancing agent?
NC-2009 EAc3:Enhanced Commissioningposted by Maya Karkour on
Hello, "X" was appointed as third party CxA by the owner, since the start of the project.
Another CxA Scenario?
NC-2009 EAc3:Enhanced Commissioningposted by Christopher Heine on
We have a project over 50,000 sf in DD phase and are in early talks with a potential Facility Manager. Can a FM or a disinterested party from that FM firm serve as a CxA for EAc3?
Document review
NC-2009 EAc3:Enhanced Commissioningposted by Adam Rustige on
Is reviewing I&O manuals and as-built drawings a requirement for enhanced commissioning? Thanks
AV systems?
NC-2009 EAc3:Enhanced Commissioningposted by Erin Holdenried on
Do AV systems need to be commissioned for LEED. Such as, if they lighting were connected to the AV system?