Hi all,
UPS system is used as a back up power in case if there is power failure. In that case. UPS itself consume small amount of power. In that case, do we include this in commisioning system?
Thanks and cheers!
Forum discussion
NC-2009 EAc3: Enhanced Commissioning
Hi all,
UPS system is used as a back up power in case if there is power failure. In that case. UPS itself consume small amount of power. In that case, do we include this in commisioning system?
Thanks and cheers!
LEEDuser is supported by our premium members, not by advertisers.
Go premium forTo post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.
mike lackey
principallackey de carvajal cx
8 thumbs up
January 30, 2011 - 3:09 pm
A UPS would not be required to be commissioned under LEED 2009. There are only four systems required to be commissioned, HVAC, Domestic Hot water, Lighting Controls and On-site Renewable Energy.
A UPS system does not fall under any of these categories.