Using Credits from Rating System Other than LEED as ID Credits
NC-v4 INc1:Innovationposted by Kathleen Gaffney on
I tried to find whether or not this question had been asked on the LEED v3 or LEED v4 comment thread but nothing seemed to rise to the surface.
Site with a mix of developed and undeveloped areas
NC-v4 SSc4:Rainwater managementposted by Ricardo Sá on
Dear All,
Option 1 requires on-site management of the runoff from the developed site for the 95th or 98th percentile of local rainfall events.
Occupant Comfort Survey and Students
Schools-NC-v4 INc1:Innovationposted by Bryna Dunn on
In v4, the innovation credit language states: "The responses must be collected from a representative sample of building occupants making up at least 30% of the total occupants." In past versi
Daylight Control In Hotel Rooms
NC-v4 EAp2:Minimum energy performanceposted by Ricardo Sá on
Dear All,
Regarding the mandatory requirements of ASHRAE 90.1 for automatic daylighting control.
Number of Lux Measurements in a High Rise Office Tower
CS-v4 EQc4:Daylightposted by Christine Recke on
In a Core and Shell project Office Tower that is over 50 stories, the rule is still measure all regularly occupied spaces in the building?
No exterior lighting
EBOM-v4 SSc4:Light pollution reductionposted by ERM Korea on
Can it achieve a point by not having any of exterior lights?
The project building does have small landscape and and rooftop garden.
Change Certification level after Preliminary Design & Construction review
CS-v4 MPR1:Must be in a permanent location on existing landposted by Ronnel Flores on
Is it allowable that for Preliminary Design & Construction (D&C) submission, the project attempt for example, Silver rating.
External Lighting in car park with uncommon typology
NC-v4 EAp2:Minimum energy performanceposted by Ricardo Sá on
Dear All,
Regarding the mandatory requirements of ASHRAE90.1 for external lighting power.
LED strip
NC-v4 SSc6:Light pollution reductionposted by Ilse Dijkstra-Nugteren on
I have a question about SSc6 and the BUG rating method. We would like to use the BUG rating method for LED strips/lines which are fixed on the facade of the project.