Defining Minimum Scope of Work of MBCx to Optimize the Investment Cost for The Building Owner
CS-v4 EAc1:Enhanced commissioningposted by Titinant on
Referring to LEED V4 EAc1 guideline, MBCx is the integration of 3 components: (1) Permanent energy monitoring systems, (2) Real-time energy analysis, (3) Ongoing commissioning.
CxA Role - Limited central plant installed
CS-v4 EAc1:Enhanced commissioningposted by Ciaran McCabe on
Monitoring-based Cx for CS projects
CS-v4 EAc1:Enhanced commissioningposted by Shannon Oletic on
What are the required measurement points for a core and shell project?
CS EA credit Enhanced Cx - who can serve as CxA
CS-v4 EAc1:Enhanced commissioningposted by Deeta Bernstein on
Any precedent in pursuing the Enhanced Cx credits with a CxA who is also the design engineer for P/FP/FA, but is not providing M/E design?
Scope of Envelope Commissioning
CS-v4 EAc1:Enhanced commissioningposted by Michelle Rosenberger on
We have a core and shell warehouse project that has no tenant buildout, i.e., no conditioned space, and therefore no thermal envelope.
Different CxA for Construction other than one hired duringDesign
CS-v4 EAc1:Enhanced commissioningposted by mohammad Hassan on
Can a different CxA for a project Construction Phase be hired other than the one hired during Design Phase ?
Building Envelope Seasonal Testing & General Comment
CS-v4 EAc1:Enhanced commissioningposted by Brian Salazar on
Hi! In general, the guidelines for this credit are...very general and vague.
Documentation upload to LEED Online
CS-v4 EAc1:Enhanced commissioningposted by Erin Rowe on
We are just getting ready to submit LEED CI V4 commissioning documents, and I noticed that it only requests that we upload the table of contents for both the Final Cx Report and Ongoing Commissioni