We are just getting ready to submit LEED CI V4 commissioning documents, and I noticed that it only requests that we upload the table of contents for both the Final Cx Report and Ongoing Commissioning Plan. I also noticed we don't have to submit the Systems Manual. I recall ALWAYS having to upload the entire thing in the older LEED version.

Just wondering if they really mean that, or can we expect to get a request the entire document during the review? Just wondering if it might be better to upload more than requested......in attempt to minimize comments.

Also - second question. My projects are in China and so much of our documentation is in Chinese (because the GC and facility staff don't speak english). We have the Cx Report and Ongoing Cx Plan in English, etc, but functional tests are in chinese. Do we need to do bilingual on those?