Can a different CxA for a project Construction Phase be hired other than the one hired during Design Phase ?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium forForum discussion
CS-v4 EAc1: Enhanced commissioning
Can a different CxA for a project Construction Phase be hired other than the one hired during Design Phase ?
LEEDuser is supported by our premium members, not by advertisers.
Go premium forTo post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.
Dave Hubka
Practice Leader - SustainabilityEUA
LEEDuser Expert
494 thumbs up
August 15, 2017 - 8:18 pm
GBCI may allow this however it would require the project team to provide an explanation as to why this was the case and probably demonstrate that a change in CxA was due to an unforeseen event (e.g. company dissolves, financial issues, death, etc.).