CS-v4 EAc1:Enhanced commissioning

Different CxA for Construction other than one hired duringDesign

Can a different CxA for a project Construction Phase be hired other than the one hired during Design Phase ?

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Wed, 08/16/2017 - 00:18

GBCI may allow this however it would require the project team to provide an explanation as to why this was the case and probably demonstrate that a change in CxA was due to an unforeseen event (e.g. company dissolves, financial issues, death, etc.).