We have a core and shell warehouse project that has no tenant buildout, i.e., no conditioned space, and therefore no thermal envelope. We interpret the vague requirements for envelope commissioning to be that the Owner and BECx together determine what kind of testing is appropriate for the building type - in this case envelope inspections, window testing and roof adhesion testing. This scope is reflected in the OPR. However, there is significant concern that the minimal scope of this work no matter how appropriate to the project is not sufficient for LEED requirements. Are we correct in our interpretation that it is in fact the Owner who determines what constitutes envelope commissioning for his building? And that whatever the agreed upon scope of this work turns out to be, if performed per NIBS guidelines, will be sufficient for LEED compliance?