Modeling Proposed DHW with Insulation

NC-v4 EAp2:Minimum energy performance
posted by  Rajat Wadhwa  on 

Hi I am Modeling a DHW system and most of my savings are coming from Insulation in the heater tank, now the LEED reviewer said that the savings should be modeled with Exceptional Calculation MEthod

4
Wed Jan 31, 2024, 10:32 pm

How to report High COP values for Chillers

NC-v4 EAp2:Minimum energy performance
posted by  Rajat Wadhwa  on 

Hi I am working on a Data Center in Chicago, and we have Chillers which have a high COP when the ambient temperature is low outside, so The energy modeling software that I am using can ony get as h

1
Fri Apr 5, 2024, 2:59 pm
4
Default Avatar
Mechanical Engineer
WSP
LEEDuser Basic Member
2 thumbs up
Fri Jan 12, 2024, 6:33 pm

Building Entrance Vestibule Requirements

NC-v4 EAp2:Minimum energy performance
posted by  Christopher Russell-King  on 

Hello! I have a question regarding the inclusion of Vestibules (double entrances to buildings to prevent heat loss), in a Court House building project we’re working on.

5
Mon Nov 27, 2023, 4:53 pm

MEPC Data Center Calculator Example

NC-v4 EAp2:Minimum energy performance
posted by  Rajat Wadhwa  on 

Hi I am looking for example for MEPC Data Center Calculator, I dont have any experince filling that sheet, can someone guide me where should I look at ?

 

TIA 

1
Wed Nov 8, 2023, 2:29 pm
3
Co-founder
Mimta EcoYapi
LEEDuser Basic Member
133 thumbs up
Mon Oct 30, 2023, 9:47 pm

District heating prices

NC-v4 EAp2:Minimum energy performance
posted by  Azra   on 

Hello,
Does anyone know if we are able to deduct from energy prices (gas) if district heating is using only 50% of gas for heating and rest comes form renewable sources?
Thanks!

4
Wed Oct 25, 2023, 1:10 pm

Data Center LEED Comment for PUE modeling

NC-v4 EAp2:Minimum energy performance
posted by  Rajat Wadhwa  on 

Hi , I submitted a Data center for LEED review in which I assumed that Data center load is operating is 100% at all the times in a year, now LEED is saying that I need to create 3  model one w

1
Wed Oct 18, 2023, 2:45 pm