Drawing Review
NC-v4 EAp1:Fundamental commissioning and verificationposted by Steve Connelly on
Is a drawing review of the building envelope required by EAp1 Fundamental Cx if Enhanced Option 2 is not being pursued?
Envelope Design Review for LEED V4 Commissioning under Fundamental Cx
NC-v4 EAp1:Fundamental commissioning and verificationposted by Rohit Upadhyay on
Hi Everyone,
Can someone clarify what is the extent of envelope design review by a Commissioning Authority (CxA)
1) Fundamental Commissioning
2) Enhanced Commissioning
Phased Cx for a phased project
NC-v4 EAp1:Fundamental commissioning and verificationposted by Peter Doo on
We are working on a comprehensive renovation and addition of an Art Center at an independent high school.
Current Facilities Requirements and O&M Plan
NC-v4 EAp1:Fundamental commissioning and verificationposted by Chris Bennett on
I am trying to determine if there a specific requirements regarding how the Current Facilities Requirements and O&M Plan is provided.
Daylight Sensor and/or Occupancy Sensor
NC-v4 EAp1:Fundamental commissioning and verificationposted by Purva Saxena on
Are primary side-lighted areas to be provided with Daylight Sensor, even though these spaces (conference room, meeting rooms, private cabins with area less than 250 sq.
Additions to Existing Cold Storage Facility
NC-v4 EAp1:Fundamental commissioning and verificationposted by Dustin Norton on
I am working on a project that includes a large existing cold storage facility that will essentially double in size after renovations.
Core & Shell with HVAC as future / CI scope
NC-v4 EAp1:Fundamental commissioning and verificationposted by Stacey Olson on
If a project is a cold, dark shell without hot water, can commissioning be deferred as n/a or does a cxa still need to be engaged to preform OPR and BOD review?
Future spaces for expansion vs date of certification
NC-v4 EAp1:Fundamental commissioning and verificationposted by Víctor Ramírez Orozco on
we are designing a school project with 14 classrooms and 5 more classrooms planned for future expansión of the school. Those 5 classrooms will not have anything but the walls, windows, and doors.
Retro-commission an existing PV array?
NC-v4 EAp1:Fundamental commissioning and verificationposted by Deborah Lucking on
Our project is a county-owned building which will utilize renewable energy from an existing, adjacent, county-owned PV farm.
CxA experience
NC-v4 EAp1:Fundamental commissioning and verificationposted by daniel vasquez on
Regarding the experience the CxA must have,
The CxA must have two previous experiences being the CxA of two similar projects or being just part of the Cx process is enough?