Drawing Review

NC-v4 EAp1:Fundamental commissioning and verification
posted by  Steve Connelly  on 

Is a drawing review of the building envelope required by EAp1 Fundamental Cx if Enhanced Option 2 is not being pursued?

16
Senior Sustainability Manager
JLL
LEEDuser Basic Member
10 thumbs up
Sat May 25, 2019, 4:12 am

Envelope Design Review for LEED V4 Commissioning under Fundamental Cx

NC-v4 EAp1:Fundamental commissioning and verification
posted by  Rohit Upadhyay  on 

Hi Everyone,

Can someone clarify what is the extent of envelope design review by a Commissioning Authority (CxA)

1) Fundamental Commissioning

2) Enhanced Commissioning

1
Sun Aug 11, 2019, 10:06 pm

Phased Cx for a phased project

NC-v4 EAp1:Fundamental commissioning and verification
posted by  Peter Doo  on 

We are working on a comprehensive renovation and addition of an Art Center at an independent high school.

1
Sun Aug 11, 2019, 10:13 pm

Current Facilities Requirements and O&M Plan

NC-v4 EAp1:Fundamental commissioning and verification
posted by  Chris Bennett  on 

I am trying to determine if there a specific requirements regarding how the Current Facilities Requirements and O&M Plan is provided.

2
Practice Leader - Sustainability
EUA
LEEDuser Expert
510 thumbs up
Thu Mar 28, 2019, 3:02 pm

Daylight Sensor and/or Occupancy Sensor

NC-v4 EAp1:Fundamental commissioning and verification
posted by  Purva Saxena  on 

Are primary side-lighted areas to be provided with Daylight Sensor, even though these spaces (conference room, meeting rooms, private cabins with area less than 250 sq.

0

Additions to Existing Cold Storage Facility

NC-v4 EAp1:Fundamental commissioning and verification
posted by  Dustin Norton  on 

I am working on a project that includes a large existing cold storage facility that will essentially double in size after renovations.

2
Sustainability Program Manager
Primus Design Services, LLC
LEEDuser Premium Member
40 thumbs up
Wed Jan 23, 2019, 7:49 pm

Core & Shell with HVAC as future / CI scope

NC-v4 EAp1:Fundamental commissioning and verification
posted by  Stacey Olson  on 

If a project is a cold, dark shell without hot water, can commissioning be deferred as n/a or does a cxa still need to be engaged to preform OPR and BOD review?

0

Future spaces for expansion vs date of certification

NC-v4 EAp1:Fundamental commissioning and verification
posted by  Víctor Ramírez Orozco  on 

we are designing a school project with 14 classrooms and 5 more classrooms planned for future expansión of the school. Those 5 classrooms will not have anything but the walls, windows, and doors.

0

Retro-commission an existing PV array?

NC-v4 EAp1:Fundamental commissioning and verification
posted by  Deborah Lucking  on 

Our project is a county-owned building which will utilize renewable energy from an existing, adjacent, county-owned PV farm.

1
Wed May 16, 2018, 1:05 pm

CxA experience

NC-v4 EAp1:Fundamental commissioning and verification
posted by  daniel vasquez  on 

Regarding the experience the CxA must have,

The CxA must have two previous experiences being the CxA of two similar projects or being just part of the Cx process is enough?

2
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Wed Jan 24, 2018, 8:22 pm