Cold Storage for Exceptional Calculation Method

NC-v4 EAp2: Minimum Energy Performance
posted by Eric Kim on May 21, 2021, 3:43 am

Hello,

I am conducting Whole Building Energy Simulation of Cold Storage Project. The program simulation trace 700.6.3.5.1 is using.

This program cannot reflect (Interpretation#10424...

Last reply: Marcus Sheffer, May 28, 2021, 3:50 pm

thermal control for the energy saving

Pilot-Credits EQpc114: Learning controls for thermal comfort
posted by Jinyong Song on Jan 2, 2020, 8:01 pm

Thermal comfort and energy saving seem to be closely related.

For a store project, energy saving is required more than thermal comfort of space.

Actually in Korea, we regulate...

how do you manage providers that provide the right materials for LEED?

Pilot-Credits SSpc55: Bird collision deterrence
posted by kim sung on Oct 27, 2019, 10:29 am

Hello.

There is a question as a preliminary contractor for bird collision deterrence.

If I had a way to lower a threat factor to 15 or less as an alternative to bird collision,...

Last reply: Stephanie Graham, Dec 4, 2019, 6:23 pm

1/4 mile radious from building boundary

CI-v4 LTc2: Surrounding density and diverse uses
posted by ERM Korea on Jan 31, 2018, 7:31 pm

Hello! I would like to ask about the 1/4 mile radius from building boundary. I have already read the article on FAQ and the one which Emily wrote, but I have a small confusion on it.

When...

Last reply: Alara Brinton, Dec 7, 2018, 1:39 pm

Baseline System selection for Datacenter

Data-Centers-NC-v4 EAp2: Minimum Energy Performance
posted by J.W. Shin on Aug 21, 2018, 5:20 am

Hi every one, Marcus

I am doing data center energy modeling for LEED V4.

The data center is composed of 3 type spaces.

Usage : dedicated data center

...

Last reply: Marcus Sheffer, Aug 21, 2018, 3:49 pm

About Spray adhesives, Material has voc g/l limit and Greenguard certificate.

NC-2009 IEQc4.1: Low-emitting materials - adhesives and sealants
posted by Eunjoo Park on Apr 23, 2018, 8:39 am

My project is located in South Korea, so I open fall into difficulties to interpret manufacture data. 

About Spray adhesives, material has voc g/l  limit and Greenguard certificate. 

...

Spray adhesives has VOC Contents and GREENGURAD certificate also. This material can be use?

NC-2009 IEQc4.1: Low-emitting materials - adhesives and sealants
posted by Eunjoo Park on Apr 23, 2018, 8:54 am

My project located in South Korea. So I often fall into difficulties to interpretation manufacture data.

The material is "Scotch-WeldTM Hi-Strength Postforming 94 CA".

As per the...

Charging station being networked to encourage off-peak charging

NC-v4 LTc8: Green vehicles
posted by ERM Korea on Feb 13, 2018, 1:53 am

Dionisio Franca Senior Consultant Woonerf Inc. LEEDuser Premium Member 24 thumbs up February 13, 2018- 2:20 am Hi Jeong, The LEED Online did not ask for demand-response participation, only for a charger that is addressable. Please read this thread too:  https://leeduser.buildinggreen.com/forum/grid-interactive-charging-stations I hope this helps. Log in or register to post comments ...

Last reply: Dionisio Franca, Feb 13, 2018, 2:20 am

25 feet (7.5 meter) Smoking Prohibition

EBOM-v4 EQp2: Environmental tobacco smoke control
posted by Wes Baek on Nov 10, 2017, 12:25 am

Hi all,

Is there any alternative when our team cannot implement 25 feet smoking prohibition policy due to a restricted project area?

Last reply: Trista Brown, Nov 21, 2017, 6:41 pm

EB Certification process before the construction is finished

Performance Period
posted by JEONGJAE LEE on Sep 21, 2017, 12:59 am

Hello, I have a question about the EB certification process since it is my first job having work on O+M project. I would be very thankful if I would be able to get any answer on it here.

...

Last reply: Trista Brown, Nov 16, 2017, 6:41 pm