Forum discussion

CS-v4 EAp2:Minimum energy performance

Minimum Energy Performance Review Phase

Hello,
I have a question about the project review.
Our project was conducted by Spilt Review.

Currently, Design Final Review is in the Division stage.
In the Design Final Review, 7 points were Denied as comments on TSLA for Minimum Energy Performance, EA.
We solved the comment on this.


Then, can I submit it to the Construction Review Phase? Or do I have to do Appeal?

 

Best Regards,

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Tue, 02/15/2022 - 14:29

All credits get two reviews, preliminary and final, after that you must appeal. If you have accepted the design final review then you have to appeal. If you have not accepted it then you can send a project team inquiry to challenge some or all of the comments but in this case you should be able to prove that the reviewer was incorrect about any changes requested. In short if the reviewer was correct then you must appeal to get a third review.

Tue, 02/15/2022 - 23:56

Thank you for your answer. Marcus,
It helped a lot.