Energy Modeling using “HAP”NC-2009 EAp2: Minimum Energy Performanceposted by Muzamil Rafique on May 27, 2016, 2:50 am
I am doing the energy model for a project. The project total area is “153,145 sf”, 25,346 sf area of the total area is condition and the other “127,799” sf area is unconditioned, “ventilation fan... Last reply: Marcus Sheffer, Mar 26, 2024, 7:46 pm |
|
Modeling only conditioned areaNC-v4 EAp2: Minimum Energy Performanceposted by Omar Elrawy on Dec 9, 2020, 10:05 pm
I'm certifying a huge factory with an attached office building. Is it possible to model only the office area? Last reply: Farooq Saeed, Mar 25, 2024, 1:38 am |
|
Can New Construction project use requirement of Warehouse and Distribution center to count point?NC-v4 LTc4: Surrounding density and diverse usesposted by Michael on Jan 10, 2023, 6:16 am
Hi LEED expert, my project is a manufacturing plant with a warehouse. The warehouse accounts for 46% of the total GFA. The project will be registered under New Construction. For this credit... Last reply: Dave Hubka, Mar 13, 2024, 10:03 pm |
|
Building will be used by the client, not be leased to 3rd party. need of "tenant design & construction guidelines document"?CS-2009 SSc9: Tenant Design and Construction Guidelinesposted by prudhvi mahadev on Feb 7, 2018, 1:03 am
hello, im pursuing a project which is going with the rating LEED 2009 C&S. i have a question, in my case the owner himself will use the space for his own purpose and will not be leased... Last reply: , Mar 5, 2024, 7:24 am |
|
What is the Exact Definition of A Trip?NC-v4 LTc5: Access to quality transitposted by Krithikha Muthukrishnan on Nov 16, 2017, 5:19 am
I am posting this question largely because the credit langauage is not very clear(maybe language nativity issues here). In the Reference Guide, "A Trip" is defined as follows- A trip... Last reply: Shadi Abousamra, Mar 4, 2024, 9:29 am |
|
How can I register a Resort Project with multiple distinct physical structures with one exceeding 25000 Sq.ft.? Description: I uHospitality-NC-v4 MPR2: Must use reasonable LEED boundariesposted by Manzil Shrestha on Feb 18, 2024, 10:50 am
How can I register a Resort Project with multiple distinct physical structures with one exceeding 25000 Sq.ft.? |
|
Allignment with WELL Preconditions?Pilot-Credits EQpc105: Lead Risk Reductionposted by Sheena Moses on Jul 26, 2023, 11:01 pm
We have attempted this credit for our office project based as we find that the requirements of 3 separate WELL preconditions and 1 optiimzation are well aligned with the requirements of this... Last reply: Thomas Lagarde, Feb 13, 2024, 11:25 am |
|
Projects with several distinct structuresHospitality-NC-v4 MPR3: Must comply with project size requirementsposted by Manzil Shrestha on Feb 13, 2024, 5:07 am
"Any single... |
|
FEES FOR BASEMENT AREALEED v4.1 Discussion Forumposted by Subrota Roy on Feb 6, 2024, 4:21 am
Is it necessary to calculate the basement area when we calculate the... |
|
Multilevel lighting controlNC-v4.1 EQc6: Interior lightingposted by Michael on Jun 26, 2022, 11:55 pm
I have 10 lighting fixtures in an office space, and the architect is providing 3 on-off switches: - switch 1, on-off 5 lightings (50% of lighting numbers) - switch 2, on-off 2... Last reply: Karen Joslin, Dec 18, 2023, 12:51 pm |