The baseline flow rate for

CI-2009 WEp1: Water Use Reduction
posted by kyle atkinson on Nov 1, 2010, 1:50 pm

The baseline flow rate for lavatory sinks was reduced from 2.5 GPM to 0.5 GPM following after 2009.
The bathroom in my project has an existing bathroom and we are changing out fixtures....

Last reply: Tristan Roberts, Nov 2, 2010, 11:05 pm

green roof exemplary performance

NC-2009 SSc7.2: Heat island effect - roof
posted by Kim Sosalla-Bahr on Nov 2, 2010, 1:23 pm

I have a question about meeting exemplary performance for credit SS 7.2. The reference guide states that, " Projects may earn an Innovation in Design credit for exemplary performance by...

Last reply: Tristan Roberts, Nov 2, 2010, 10:52 pm

Missing zip codes

EBOM-2009 RPc1: Regional Priority
posted by Abigail Johnson on Nov 2, 2010, 8:07 pm

My project is located in 23707 in Hampton Roads Virginia. It is not listed in the...

Last reply: Tristan Roberts, Nov 2, 2010, 9:20 pm

Documentation

EBOM-2009 MRc5: Sustainable purchasing - food
posted by Andreas Hintz on Oct 1, 2010, 8:07 am

Hi, I`m working on an office building to gain LEED...

Last reply: Natalie Bodenhamer, Nov 2, 2010, 6:48 pm

re: documenting a credit from another LEED rating system

CI-2009 IDc1: Innovation in Design
posted by Cara Mae Cirignano on Nov 2, 2010, 2:13 pm

Hi Leonard -
Just hit the feedback button in LEED Online, and provide all the relevant information: your project name/number, which form you are looking for, and a description of why you...

LEED Online and non-US RPC's

General forums
posted by Cara Mae Cirignano on Nov 2, 2010, 1:54 pm

Thanks everyone for your comments. If a project has Regional Priority credits that are inconsistent with those publicly announced, USGBC asks that project team members use the LEED Online...

Can i go for LEED CI?

LEED Rating System Selection
posted by Simon Sue on Oct 28, 2010, 8:44 pm

I been asked and i did not have a definite answer for this, i have a client, who will build his own office tower and he asked whether is possible to certify one of the tower floor with LEED CI...

Last reply: Simon Sue, Nov 1, 2010, 9:01 pm

Upload requires WEP1-1 which

CS-2009 WEp1: Water Use Reduction
posted by eileen hughes on Oct 22, 2010, 9:47 am

Upload requires WEP1-1 which is a plumbing fixture & fitting schedule.
We cannot complete this document since fixtures will be provided under tenant fitout. I've checked special...

Last reply: Karen Blust, Nov 1, 2010, 7:36 pm

Multi-floor tenant- LEED CI project on single floor

CI-2009 SSc3.2: Alternative transportation - bicycle storage and changing rooms
posted by Susan M. Kaplan on Oct 25, 2010, 6:02 pm

We're working on a project in a building in which the client is already occupying several floors. They have bike storage on the ground floor dedicated solely to employees of the company (but not...

Last reply: Susan M. Kaplan, Nov 1, 2010, 10:27 am

Do charging rooms for fork lifts fall under this credit?

NC-2009 IEQc5: Indoor Chemical and Pollutant Source Control
posted by Christian Brücher on Oct 27, 2010, 2:21 am

We have a warehouse / distribution center we would like to certify. There is a charging room for the fork lifts (and therefore a unlikely but possible risk of hydrogen production). Do you think...