Home Office ProjectsPilot-Credits INpc136: Safety First: Re-Enter Your Workspaceposted by Mayela Saucedo on Jan 25, 2024, 2:13 pm
To meet the requirements of the 'Re-Enter Your Workspace' credit, daily surveys are mandatory, covering aspects such as social distancing. However, some projects post-pandemic have adopted hybrid... |
|
Submetering the pool and dialysisNC-v4 WEc4: Water meteringposted by Eslam Elshorbagy on Jan 25, 2024, 11:56 am
Hi. We have a building that is half a fitness facility and the other half a medical clinic. We intend to submeter the pool in the fitness facility and the dialysis equipment in the... |
|
Purchasing Policy PrerequisiteEBOM-v4.1 MRp1: Purchasing Policyposted by Sean Smith on Jan 25, 2024, 10:32 am
I'm working on a project where the property manager told us the only on-going purchases for the buliding are cleaning supplies (brooms, garbage bags, gloves) and all other purchases are tenant... |
|
Chemical inventory of the product, HPD.NC-v4.1 MRc4: Material Ingredientsposted by T Ros on Jan 25, 2024, 10:05 am
If an HPD inventory includes the following information: "Substances representing 95% of the product weight are reported at 100/1000 ppm threshold and substances representing 5% of the product... Last reply: Tommy Linstroth, Jan 25, 2024, 10:16 am |
|
TVOC rangesNC-v4.1 EQc2: Low-emitting materialsposted by Karim Farah on Jan 24, 2024, 4:46 pm
Hello, I am seeking clarification on a specific requirement mentioned in LEED V4.1 EQ Credit: Low Emitting Materials, specifically on page 235. The document mentions that... Last reply: Denise Bevilaqua, Jan 24, 2024, 6:39 pm |
|
How to tell if the chemical inventory of a product is disclosed to 0.1% (1000ppm)NC-v4 MRc4: Building product disclosure and optimization - material ingredientsposted by Ashley Hu on Jun 19, 2018, 7:51 pm
Hello there, Option 1 accepts the following as documentation:
Last reply: Megan Bodin, Jan 24, 2024, 5:21 pm |
|
Meeting EAp2 in LEED oWarehouses-EBOM-v4 EAp2: Minimum Energy Performanceposted by Ralph Bicknese on Jan 24, 2024, 1:19 pm
We are evaluating utilizing LEED O+M for Warehouses and Distribution Centers for a 1.5M sf Distribution Center where the all parties are very interested in being able to achieve a LEED rating and... |
|
Surface Testing ProcessPilot-Credits INpc137: Cleaning and Disinfecting Your Space for Emerging Pathogensposted by Zeynep Cakir on Dec 29, 2020, 7:35 am
Dear fellows, Does anyone have any idea or recommendations on how to determine the surface cleanliness? How should we perform the quantitative testing? What kind of tools or equipment will... Last reply: Torsten Biernat, Jan 24, 2024, 10:41 am |
|
Additonal Interior Lighting PowerRetail-CI-v4 EAc2: Optimize Energy Performanceposted by James Pack on Jul 1, 2020, 7:11 am
We are trying to calcuate the additional allowance for Display Lighting in a Jewellery store. When calcualting the allowance does the W/ft2 cover the individaul display area (display shelves /... Last reply: Marcus Sheffer, Jan 23, 2024, 6:03 pm |
|
Additional Interior Lighting PowerCS-v4 EAp2: Minimum Energy Performanceposted by Ricardo Sá on Nov 22, 2016, 9:21 am
Hi all, I'm currently working in a project of shopping mall (common areas + tenant areas) pursuing LEED certification (Core&Shell). In tenant areas, a relevant part of the total... Last reply: Marcus Sheffer, Jan 23, 2024, 6:02 pm |