Multiple Drainage Patterns

NC-2009 SSc6.1: Stormwater design - quantity control
posted by Joseph Blanco on Feb 7, 2011, 3:14 pm

Can you tell me how to calculate for multiple draingage sites, i have Three on this particular project. The TC is based on the length and travel and the slope towards the discharge point . Do i...

Last reply: Gregory Hurst, Feb 8, 2011, 2:37 pm

Equipment Purchases

EBOM-2009 IEQp3: Green Cleaning Policy
posted by Curt Pascoe on Feb 8, 2011, 11:03 am

We are implementing a Green Cleaning Policy for an ID credit in NCv2009, which simply requires that you meet this prerequisite (not Credits 3.3 & 3.4). However, despite being NC, this...

Last reply: Curt Pascoe, Feb 8, 2011, 2:08 pm

Elevator cabs

Schools-2009 IEQc4.6: Low-Emitting Materials—Ceiling and Wall Systems
posted by Linda Davisson on Feb 8, 2011, 12:10 pm

Often the finishes in an elevator cab are inert materials/non-emitting such as metal panels for walls and plastic unit lighting for ceilings. In the case of plastic laminate panels, the materials...

Last reply: Josh Jacobs, Feb 8, 2011, 1:51 pm

Indoor/Outdoor Carpeting in Large Open-Air Tropical Lobby

EBOM-2009 IEQc3.5: Green cleaning - indoor chemical and pollutant source control
posted by Terry Gorski on Feb 4, 2011, 12:48 pm

For a building located in a tropical climate with an open- air lobby around the elevator banks, would indoor/outdoor carpeting completely under the cover of the building meet the requirements?...

Last reply: Tristan Roberts, Feb 8, 2011, 12:13 pm

waste cycle and deskside recycling

EBOM-2009 MRc6: Solid waste management - waste stream audit
posted by Wendy Gibson on Jan 25, 2011, 5:33 pm

We are currently trying to determine an adequate and manageable approach to this credit. Here is our scenario
- We currently have daytime janitorial service (6am – 2:30pm).
- Trash is...

Last reply: Wendy Gibson, Feb 8, 2011, 12:11 pm

Exemplary Performance

NC-2009 IEQc8.2: Daylight and views - views
posted by Lee Dingemans on Feb 7, 2011, 2:47 pm

Question
This credit has been reviewed and approved during preliminary design review of this project. Some other credits had not been approved but where subsequently approved during final...

Last reply: Carlie Bullock-Jones, Feb 8, 2011, 11:06 am

Building types

NC-2009 EAc1: Optimize Energy Performance
posted by Jeff Riggs on Jan 21, 2011, 4:14 pm

We are working on a materials recycling facility that will be comprised of a two story office building (administration) and a large materials handling space (100,000 sf+) that is attached. The...

Last reply: Marcus Sheffer, Feb 8, 2011, 9:25 am

How long does the monthly monitoring last for?

Pilot-Credits WEpc17: Cooling tower water use
posted by William Wong on Jan 26, 2011, 10:58 pm

One of the mentioned requirements is to report results of the amount of potable water used, microbiological levels, blowdown and corrosion on monthly basis, but for how long after occupancy?

Last reply: Christina Macken, Feb 8, 2011, 9:24 am

LEED-CS for apartment

CS-2009 EAc1: Optimize Energy Performance
posted by Chaan Ah Bahk on Feb 7, 2011, 4:54 am

We are looking forward to pursue LEED for an apartment building(only residential, of which each residential units will be sold to different tenants.
We are wondering whether this case can...

Last reply: Marcus Sheffer, Feb 8, 2011, 8:42 am

10% exemption?

EBOM-2009 IEQp1: Minimum indoor air quality performance
posted by Alice Cook on Jan 26, 2011, 5:43 pm

I'm unclear if 10% of space can be exempted for this prerequisite. Could someone clarify this? We have a project where we have several retail spaces on the ground floor of an office high rise...