Log in
Forum
Topic

Limit Boundary-

NC-2009 SSp1: Construction Activity Pollution Prevention
posted by gabriel Morales on Dec 6, 2010, 5:42 pm

The project is located on a 2.67 ha L-shaped site and it consists on the following:
• 4 underground levels of parking
• 3 levels of retail (covering the entire site)
• 3 towers...

Last reply: Tristan Roberts, Dec 28, 2010, 9:45 pm

Elaras Question- LEED Certification for High-Rise Multi-family

General forums
posted by Dan Ackerstein on Dec 28, 2010, 7:09 pm

In theory, EBOM...

gross floor area

General forums
posted by Tristan Roberts on Dec 28, 2010, 6:19 pm

No, I don't think you need to include this, just as you wouldn't include an outdoor parking lot. It's not occupied space.

Outdoor Air delivery monitoring with increased ventilation rate

CI-2009 IEQc1: Outdoor Air Delivery Monitoring
posted by Suraj Shah on Dec 21, 2010, 4:36 am

How does the alarming system work if the project is attempting IEQ credit 2, wherein 30% extra fresh air is provided? Does the set point then change to the designed fresh air quantity & then...

Last reply: Tristan Roberts, Dec 28, 2010, 6:12 pm

No adhesives used on a project

CI-2009 IEQc4.1: Low-emitting materials - adhesives and sealants
posted by ari meisel on Dec 14, 2010, 4:00 pm

I have a CI project isn't using ANY adhesives, I believe we meet the intent of the credit but it's not an option, anyone had that situation?

Last reply: Tristan Roberts, Dec 28, 2010, 6:08 pm

Linoleum production in USA

CI-2009 MRc6: Rapidly Renewable Materials
posted by Linda Davisson on Dec 20, 2010, 2:35 pm

I heard a rumor that linoleum may once again be manufactured in the USA. Anyone know a US manufacturer, or why linoleum is not manufactured in the USA?

Last reply: Tristan Roberts, Dec 28, 2010, 6:06 pm

SSC1 path 9, Innovative waste water technology

CI-2009 SSc1: Site Selection
posted by Jorng-ren Chern on Oct 7, 2010, 5:14 am

I have chosen to use the Option 1 to document the credit, but the SSc1 template seems to be “WRONG” in the following areas:

1. On the template it says: “The baseline for WE Credit 2 is...

Last reply: Tristan Roberts, Dec 28, 2010, 5:50 pm

required documentation

CS-2009 EAc3: Enhanced Commissioning
posted by Tatjana Ernst on Dec 10, 2010, 4:24 am

we have an CS-Building with an...

Last reply: Chris Ladner, Dec 28, 2010, 5:47 pm

Secure bicycle racks

CS-2009 SSc4.2: Alternative transportation - bicycle storage and changing rooms
posted by Yelena Gipsov on Dec 20, 2010, 7:06 pm

What should be considered as a secure bicycle racks for Commercial Projects 300,000 s.f. or less (vs. non-secure)?

If provided racks are outside, do they have to be fully covered?
...

Last reply: Tristan Roberts, Dec 28, 2010, 5:37 pm

ASHRAE Level II audit-Ok to submit for EAp1?

EBOM-2009 EAp1: Energy efficiency best management practices - planning, documentation and opportunity assessment
posted by Alice Cook on Dec 28, 2010, 5:20 pm

We hired an outside engineer to perform a level II audit. We essentially skipped the level one writeup and just ensured our final report included both level I and II requirements. Is it okay to...

Last reply: Tristan Roberts, Dec 28, 2010, 5:30 pm