Two fan systems on a common supply riserEBOM-2009 IEQp1: Minimum indoor air quality performanceposted by Dave Munn on Dec 4, 2009, 2:30 pm
We are working on a building with a supply fan both at the top of a common supply duct riser (penthouse) and another supply fan in the lower level connected to the base of the common riser. Both... Last reply: Jalal Avades, Mar 24, 2011, 1:47 am |
|
Multiple AHUs serving a single spaceEBOM-2009 IEQp1: Minimum indoor air quality performanceposted by Zachary Goodnough on Feb 23, 2011, 1:47 am
The building I am working on has a large main sales area which is served by 8 AHUs, all bringing in 100% fresh air. In this case, is the proper protocol to first divide total peak customer and... Last reply: Zachary Goodnough, Mar 23, 2011, 11:07 pm |
|
Applicability of Pilot CreditsUsing the LEED Pilot Credit Libraryposted by Abena Darden on Mar 18, 2011, 5:55 pmTristan-We've just registered for Pilot Credit 11 in a LEED for Homes project but I notice on the applicability table above this credit cannot be used for Homes. Is this a hard and fast USGBC... Last reply: Batya Metalitz, Mar 23, 2011, 5:19 pm |
|
EAp2 Equipment MotorsCI-2009 EAp2: Minimum Energy Performanceposted by Eric Claycamp on Mar 22, 2011, 11:23 am
For a LEED CI project that includes a fitness center, do you count the motors in the treadmills and cross trainers? No fitness equipment I have found is Energy Star rated. These loads can be... Last reply: David Hubka, Mar 23, 2011, 5:09 pm |
|
EAc1 required 2 pointsCI-2009 EAp2: Minimum Energy Performanceposted by Jennifer Berthelot-Jelovic on Mar 22, 2011, 3:41 pm
I know that for EAc1 there was a requirement that "All LEED for New Construction project registered after June 26, 2007 are required to achieve at least two (2) points." Since I am working on a... Last reply: David Hubka, Mar 23, 2011, 5:05 pm |
|
Design Engineer SignatoryCI-2009 EAp2: Minimum Energy Performanceposted by Sundararaj Subburaman on Mar 23, 2011, 3:11 am
Please let me know if the HVAC Designer will be representing the Design Engineer Signatory for the EA P2? If not who will be the Design Engineer - MEP designer? Last reply: David Hubka, Mar 23, 2011, 5:00 pm |
|
Credit 3.2, Option 1, Path 2NC-2009 IEQc3.2: Construction IAQ management plan - before occupancyposted by Douglas Blakeslee on Mar 21, 2011, 4:35 pm
We are the... Last reply: David Hubka, Mar 23, 2011, 10:02 am |
|
Supplemental DocumentsGeneral forumsposted by David Eldridge on Mar 22, 2011, 9:46 pm
If your normal process was to generate letter size documents for the project, then I don't see why... |
|
Hotel with a Conference Center and EnergyStarEBOM-2009 EAp2: Minimum Energy Efficiency Performanceposted by Jalal Avades on Nov 11, 2010, 6:07 pm
My project(s) is a Hotel Building with an adjacent Conference Center those are connected by a Tunnel. The Central Plant which house the chillers, heating hot water boilers, domestic hot... Last reply: Jalal Avades, Mar 22, 2011, 2:15 pm |
|
Commissioning process in a volume programGeneral forumsposted by Emmanuel Pauwels on Mar 22, 2011, 1:00 pm
After reading the documentation about the LEED Volume program, I understand that it is essential to implement a quality control plan in order to ensure that the certified prototype will be... Last reply: Tristan Roberts, Mar 22, 2011, 1:29 pm |