After reading the documentation about the LEED Volume program, I understand that it is essential to implement a quality control plan in order to ensure that the certified prototype will be implemented consistently. Thas is very similar to the objective of the commissioning process, althout on a larger scale. My question is : Is it necessary to implement a commissioning process everytime there a store is build, or is commissioning integrated in that overall quality control plan?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Tristan Roberts
RepresentativeVermont House of Representatives
LEEDuser Expert
11478 thumbs up
March 22, 2011 - 1:29 pm
Emmanuel, if I understand your question correctly, every building must be commissioned to comply with EAp1 and EAc3, if EAc3 is being pursued.