Smoking PolicyNC-2009 IEQp2: Environmental Tobacco Smoke (ETS) Controlposted by Doreen Kruschina on Apr 4, 2012, 6:22 am
I have a project in which two outside smoking areas are planed, the first one is for the worker of the plant and is much far away from windows and doors of the plant than necesary, the second one... Last reply: Tristan Roberts, Apr 6, 2012, 3:35 pm |
|
Material reuseNC-2009 MRc3: Materials Reuseposted by Ameet AA on Mar 19, 2012, 11:47 am
If the materials are to be reused, ship from another country would it assist for attaining any LEED Credits? As i understand it would not be sustainable in terms of carbon emission. Last reply: Tristan Roberts, Apr 6, 2012, 2:56 pm |
|
LEED NC- Tenant CommissioningCS-2009 EAp1: Fundamental Commissioning of Building Energy Systemsposted by Jennifer Preston on Feb 28, 2012, 9:07 am
Our... Last reply: Chris Ladner, Apr 6, 2012, 2:48 pm |
|
Commissioning existing energy systesCS-2009 EAp1: Fundamental Commissioning of Building Energy Systemsposted by Ken Dooley on Mar 2, 2012, 6:09 am
We have building renovation that is refurbishing 80% of a building aiming for CS 2009. There will be some existing ventilation and cooling systems that (a) have primary plant that is being... Last reply: Chris Ladner, Apr 6, 2012, 2:40 pm |
|
backup energy sourceNC-2009 EAp2: Minimum Energy Performanceposted by Francesco Passerini on Apr 6, 2012, 2:01 pm
Hello. I’m dealing with the calculation method for the credits relative to EA section. I don’t understand the meaning of the following sentence of paragraph G2.4 of ANSI/ASHRAE/... Last reply: Marcus Sheffer, Apr 6, 2012, 2:32 pm |
|
Temporary construction material left on-site.NC-2009 MRc2: Construction Waste Managementposted by Keith Robertson on Feb 27, 2012, 11:46 am
Should MRc2 include temporary construction materials that are left on-site. In particular, it is common for a crane-base, or temporary concrete dead-men or casting beds to be left on-site. In... Last reply: Tristan Roberts, Apr 6, 2012, 2:00 pm |
|
Criteria of choosing CxANC-2009 EAp1: Fundamental Commissioning of Building Energy Systemsposted by Patana Rattananavathong on Jan 25, 2012, 10:38 pm
There are about 3... Last reply: Tristan Roberts, Apr 6, 2012, 1:33 pm |
|
Waste Water Calculation for Option 2NC-2009 WEc2: Innovative Wastewater Technologiesposted by sompoche sirichote on Mar 28, 2012, 10:56 pm
LEED template use the flush fixture water which calculated based on occupant usage. But our plumbing design is based on fixture unit which includes both flush and flow fixture into the WWTP... Last reply: Tristan Roberts, Apr 6, 2012, 1:29 pm |
|
SaunaNC-2009 WEp1: Water Use Reductionposted by Jim Park on Feb 28, 2012, 5:32 am
I am working on a hotel project, which would use standard fixtures (no high-efficiency fixtures), but would still earn 2 points under WEc2, and 2 points under WEc3 due to utilizing recycled gray... Last reply: Tristan Roberts, Apr 6, 2012, 1:19 pm |
|
Previously Registered Project with New TeamGeneral forumsposted by Shannon Allison on Apr 4, 2012, 5:16 pm
We are working on a project that is going through redesign with a new project team. The project was registered during the original design. How do we assign the project to the new team? Last reply: Samantha Harrell, Apr 6, 2012, 12:46 pm |