LEED v2009
Core & Shell
Energy and Atmosphere
Fundamental Commissioning of Building Energy Systems

LEED CREDIT

CS-2009 EAp1: Fundamental Commissioning of Building Energy Systems Required

See all forum discussions about this credit »

Credit achievement rate

XX%

Upgrade to LEEDuser Premium to see how many projects achieved this credit. Try it free »

LEEDuser expert

Scott Bowman

Integrated Design + Energy Advisors, LLC
LEED Fellow

LEEDuser’s viewpoint

Frank advice from LEED experts

LEED is changing all the time, and every project is unique. Even seasoned professionals can miss a critical detail and lose a credit or even a prerequisite at the last minute. Our expert advice guides our LEEDuser Premium members and saves you valuable time.

Credit language

USGBC logo

© Copyright U.S. Green Building Council, Inc. All rights reserved.

Requirements

The following commissioning process activities must be completed by the project team:

  • Designate an individual as the commissioning authority (CxA) to lead, review and oversee the completion of the commissioning process activities.
    • The CxA must have documented commissioning authority experience in at least 2 building projects.
    • The individual serving as the CxA must be independent of the project’s design and construction management, though the CxA may be an employee of any firms providing those services. The CxA may be a qualified employee or consultant of the owner.
    • The CxA must report results, findings and recommendations directly to the owner.
    • For projects smaller than 50,000 gross square feet (4,500 gross square meters), the CxA may be a qualified person on the design or construction teams who has the required experience.
  • The owner must document the owner’s project requirements. The design team must develop the basis of design. The CxA must review these documents for clarity and completeness. The owner and design team must be responsible for updates to their respective documents.
  • Develop and incorporate commissioning requirements into the construction documents.
  • Develop and implement a commissioning plan.
  • Verify the installation and performance of the systems to be commissioned.
  • Complete a summary commissioning report.
Commissioned Systems
Commissioning process activities must be completed for the following energy-related systems, at a minimum (if they are installed as part of the core and shell project):
  • Heating, ventilating, air conditioning and refrigeration (HVAC&R) systems (mechanical and passive) and associated controls.
  • Lighting and daylighting controls.
  • Domestic hot water systems.
  • Renewable energy systems (e.g. wind, solar).
Credit substitution available
You may use the LEED v4 version of this credit on v2009 projects. For more information check out this article.
See all forum discussions about this credit »

What does it cost?

Cost estimates for this credit

On each BD+C v4 credit, LEEDuser offers the wisdom of a team of architects, engineers, cost estimators, and LEED experts with hundreds of LEED projects between then. They analyzed the sustainable design strategies associated with each LEED credit, but also to assign actual costs to those strategies.

Our tab contains overall cost guidance, notes on what “soft costs” to expect, and a strategy-by-strategy breakdown of what to consider and what it might cost, in percentage premiums, actual costs, or both.

This information is also available in a full PDF download in The Cost of LEED v4 report.

Learn more about The Cost of LEED v4 »

Addenda

2/1/2010Updated: 2/14/2015
Reference Guide Correction
Description of change:
In the first line of the fourth round bullet item under the first square bullet item, replace "b a" with "be a" so the text becomes "...the CxA may be a qualified..."
Campus Applicable
No
Internationally Applicable:
No
2/1/2010Updated: 2/14/2015
Rating System Correction
Description of change:
In the first line of the fourth round bullet item under the first square bullet item, replace "b a" with "be a" so the text becomes "...the CxA may be a qualified..."
Campus Applicable
No
Internationally Applicable:
No
7/6/2012Updated: 2/14/2015
Global ACP
Description of change:
Change "5,000" to "4,600" in the fourth sub-bullet
Campus Applicable
No
Internationally Applicable:
Yes
2/1/2010Updated: 2/14/2015
Reference Guide Correction
Description of change:
In the sixth row of the first column, replace "ofceneral" with "of general" so the text becomes "or subcontractor of general..."
Campus Applicable
No
Internationally Applicable:
No
7/1/2016
LEED Interpretation
Inquiry:

The LEED Rating system requirements for Enhanced Commissioning establish that “an independent commissioning authority (CxA) must lead, review, and oversee the completion of all commissioning process activities.” What specific responsibilities does this entail in a case where more than one CxA from separate companies are engaged to complete commissioning tasks?

Ruling:

The use of the phrase “lead, review, and oversee” defines a high level of participation while providing some flexibility for fitting the process to the project.

Therefore, at a minimum, the lead commissioning agent should be participating in ALL commissioning activities including BOTH fundamental and enhanced commissioning activities. The exact level of leading, reviewing, and overseeing can vary based on individual project scenarios. However, for enhanced commissioning, the entity selected as the lead CxA must complete the following tasks at a minimum:

Fundamental commissioning tasks to be performed by lead CxA:

• Review owner’s project requirements and basis of design during the early design phase.
• Confirm incorporation of Cx requirements into construction documents.
• Develop or approve construction checklists.
• Develop or approve system test procedures.
• Witness at least a portion of the mechanical, electrical, plumbing, and (if applicable) renewable system functional testing that verifies installation and performance of commissioned systems. Refer to ASHRAE Guideline 0 for additional guidance.
• Review an issues log throughout the Cx process. If the CxA does not directly update the log, the CxA must approve all updates to the log.
• Report findings directly to the owner throughout the process.
• Develop or approve the summary commissioning report.

Enhanced Commissioning Tasks to be performed by lead CxA:
• Conduct commissioning design review prior to mid-construction documents.
• Review contractor submittals applicable to systems being commissioned.
• Develop or approve systems manual updates and delivery.
• Verify operator and occupant training delivery and effectiveness.
• Review building operation within 10 months after substantial completion.

Campus Applicable
Yes
Internationally Applicable:
Yes
2/9/2009
LEED Interpretation
Inquiry:

The purpose of this CIR is to request an alternate compliance path for fundamental systems commissioning for the major renovation of a 10,000 sq. ft., Texas office building which is nearing the end of construction (the tenants have moved in on a temporary occupancy certificate). It has been the intent of the project team from design onset to submit the project for LEED Certification. Accordingly, substantial efforts and monies have been committed to strengthening the building envelope (from an EA standpoint), to replacing the HVAC systems with high-efficiency equipment, to installing measurement and verification equipment and for several other sustainable measures outside of the EA category. Unfortunately, due to the inexperience of some of the team members and a fast-track construction schedule, the commissioning process did not occur through the design and early construction as outlined in the reference guide. The team asks the USGBC to review the alternate commissioning strategy outlined below and to advise on whether this approach fully meets the requirements of EA Prerequisite 1: 1. Designate an individual as the CxA: The Owner has designated an employee of the MEP design firm as the CxA. The selected individual for this role is part of a specialized commissioning group within the firm and has not been involved with the design or construction of the project. He has served as the commissioning agent for several projects of similar scope and technical complexity. 2. CxA shall review Owner\'s Project Requirements and Basis of Design: The Design Team and Owner will prepare the Owner\'s Project Requirements to include Owner and User Requirements, Environmental and Sustainability Goals, Energy Efficiency Goals, Indoor Environmental Quality Requirements, Equipment and System Expectations, and Building Occupant and O & M Personnel Requirements. The Design Team will prepare a Basis of Design narrative which explains the design of the HVAC&R systems, the project lighting, the domestic hot water system, associated controls, and any additional systems requiring commissioning. The CxA will review and comment on these documents and the documents will be updated by the owner and design team respectively. 3. Develop and Incorporate commissioning requirements into the construction documents: The CxA will develop commissioning specifications which will be incorporated into the construction documents via supplemental instructions to the construction team and will become part of the construction documents. 4. Develop and Implement commissioning plan: The CxA will develop the commissioning plan which will include the Commissioning Program Overview, the Commissioning Team, and the Description of the Commissioning Process Activities. The commissioning plan will take into account that the equipment has already been installed and started up. 5. Verify Installation and performance of systems to be commissioned and complete a commissioning report: CxA will still follow all credit requirements, including pre-functional and functional testing procedures even though equipment has already been started. Deficiencies will be reported, and contractors will correct any deficiencies found during commissioning activities via supplemental instructions or under warranty. CxA will complete a summary report.

Ruling:

The project team is proposing a commissioning process to meet the requirements of this prerequisite, where the project team engages the commissioning authority in the late stages of construction after tenant occupation. The proposed process is not acceptable. The key steps of the commissioning process do not deliver the intended value if performed outside of the normal design and construction schedule. The USGBC has devised the LEED for Existing Building Operation and Maintenance Rating System for cases such as this and the project team is encouraged to consider that Rating System for this building.

Campus Applicable
No
Internationally Applicable:
No
7/10/2009
LEED Interpretation
Inquiry:

We are requesting a CIR for a commercial tenant build out in an existing space. The owner decided to go forward with LEED certification after original design drawings were in place. An independent Cx Authority was brought on board after construction documents were issued but before construction commenced, and was in contact with all necessary trades. A commissioning plan was generated prior to commissioning activities. The CxA worked with the project team throughout the construction process and generated a full Cx report. This project utilized existing mechanical equipment which serves the existing spaces. All information regarding this is outlined in the BOD. The Commissioning Agent reviewed all documents and incorporated these guidelines in their plan and final report. The built systems have had a thorough and unbiased review not just of how they were built, but of how they were designed. All prerequisite requirements have been met with the exception of the specifications being included in the original contract documents. All trades cooperated and worked with the Cx. Keeping with the intent of this prerequisite, all systems were adequately commissioned. The CxA has verified that the project\'s energy-related systems are installed, calibrated, and perform as intended, and has verified that all of the required systems are calibrated correctly and satisfy the owner\'s project requirements (OPR) and BOD.

Ruling:

The project team is requesting that the project meets the requirements for Fundamental Commissioning despite the exclusion of commission specifications being included in the original contract documents. For alternate compliance, documentation should be provided showing that the commissioning specifications were later issued and that they will be enforced by the owner and accepted by the contractor as part of the scope of work than the request is approved. Applicable Internationally.

Campus Applicable
No
Internationally Applicable:
Yes
11/27/2007
LEED Interpretation
Inquiry:

This question is in regard to a small free standing series of retail or office building. As this is not a typical building pursuing LEED CS there are a few items that we will need clarified before pursuing the certification. 1. Can we apply LEED for campuses to a series of small retail or office buildings on the same site and submit as a single application through LEED CS? 2. If we build out a single tenant suite in one of the buildings as an example for the future tenants to follow, are the credits achieved applicable to all buildings including those that have not been built out with the sample suite? 3. What extent of commissioning is required for the prerequisite/ enhanced if the units are provided, but are not powered, nor are they connected to ducts yet? 4. If we may apply LEED for campuses to the series of buildings, and submit as a single application, can multiple plaques be purchased for each building? Thank you for reviewing, the direction set by the council on this building type will impact the market for this type of construction. We appreciate your review.

Ruling:

This CIR can be divided into questions about the process for submitting using the LEED-NC Application Guide for Multiple Buildings and On-Campus Building Projects, and a question regarding the execution of EAp1 in a core and shell project. Because an individual CIR should only regard a single issue, the technical question regarding EAp1 will be addressed. For information relating to registering multiple projects simultaneously, please refer to the LEED-NC Application Guide for Multiple Buildings and On-Campus Building Projects, which can be found at: http://www.usgbc.org/ShowFile.aspx?DocumentID=1097 and USGBC customer service, if necessary. For Core and Shell (CS) projects, full commissioning should be provided for all equipment that serves common spaces (non-tenant, such as lobbies, public areas, and core restrooms if provided). For equipment that has been installed, but not powered or connected to duct work, it is left to the discretion of the agent what level of commissioning can be performed. At the very least the proper installation technique, location, and equipment type should be verified with respect to the owner\'s requirements, contract documentation, and manufacturer\'s instructions. The agent should note in their report what level of commissioning was performed on each piece of equipment and make recommendations for what additional commissioning should be performed during tenant fit-out.Update April 15, 2011: Please note that all 2009 projects in multiple building situations must follow the 2010 Application Guide for Multiple Buildings and On-Campus Building Projects, located here: https://www.usgbc.org/ShowFile.aspx?DocumentID=7987. 2009 project teams should check this document for up to date guidance on all multiple building issues. Applicable Internationally.

Campus Applicable
No
Internationally Applicable:
Yes
3/15/2007
LEED Interpretation
Inquiry:

In this CIR, we are asking for clarification on whether our selected Commissioning Agent (CxA) meets the technical requirements for compliance with the LEED prerequisite and optional point for commissioning. We believe that this arrangement is consistent with the definition of an independent consultant contracted to Owner (item #8 in the 1/3/2006 memo issued by the USGBC, "Who Can Be the Commissioning Authority"). The selected CxA\'s dual roles are as follows: Automation System Design: One of the CxA\'s roles is to assure that the automation system design for the project maintains the Owner\'s standards, which are complex and ever changing. The Owner has determined that it is far more expedient, and their deliverable more consistent, if the automation systems are designed by a small pool of engineers that remain current with the technologies and procedures that the Owner\'s Energy Management team uses (as opposed to trying to have individual A/Es be educated and brought up to speed on the ever changing requirements of the automation systems that this Owner employs). Among the duties of the automation system designer is the assurance in continuity of Owner standards for hardware, software, and communications. The selected CxA is retained directly by the Owner to perform these functions and is the Owner\'s agent for this building system; there is no contractual affiliation between the selected CxA and the project\'s A/E. The project\'s HVAC systems are designed by the A/E; the A/E bears responsibility for the design, construction, and performance of the HVAC systems. The A/E is responsible for the HVAC systems control sequences of operation and for assuring that their design can perform accordingly. The selected CxA takes the A/E\'s design and sequences and assures that control devices needed to fulfill the sequences are per Owner standards, that automation system architecture is per Owner standards, and that software routines are consistent with design intent and vice-versa. Achieving this element of the automation system design requires interaction and teamwork between the A/E and the selected CxA, but the separation remains of the selected CxA being directly responsible to the Owner for the automation system functionality and the A/E being responsible for system design and performance. Independent Commissioning: The selected CxA is retained directly by the Owner and is the Owner\'s independent agent for HVAC systems commissioning; there is no contractual affiliation with the A/E. That the selected CxA is also involved with the automation systems design enhances the effectiveness of both HVAC commissioning and automation system building management and provides and economy to the Owner in professional services fees. The selected CxA has been performing automation systems design for this Owner since 1986 and has been performing HVAC commissioning services for this Owner since 1992. The dual functions have been executed over this long standing relationship without conflict as the selected CxA is not responsible for HVAC systems design. The selected CxA has no design role in other building systems to be commissioned to satisfy LEED requirements (lighting controls, domestic hot water). Therefore, the basic argument is that the selected CxA\'s allegiance, and contractual relationship, is directly to the Owner for automation system design and commissioning services. There is no contractual affiliation between the selected CxA and the A/E design team; the selected CxA interacts with the A/E performing reviews and coordination. The Owner and design team does not perceive any conflict by the CxA performing automation system design that would exclude them from performing Fundamental or Enhanced (point credit) commissioning. We ask that the USGBC confirm that we properly interpreted the memo regarding who can be the commissioning agent as it applies to our unique situation described above.

Ruling:

EAp1 and EAc3 clearly state that the commissioning agent shall be independent from the work of design and construction. If the CxA is also designing the automation system, than the CxA does not meet the independence requirement of the commissioning prerequisite and credit. The control system should be commissioned and therefore it is important for CxA to be independent of the design of this system. Applicable Internationally.

Campus Applicable
No
Internationally Applicable:
Yes
9/18/2007
LEED Interpretation
Inquiry:

This Seattle, Washington project is a residential, fast-track high-rise and is currently in the early stages of construction. While the project team recognizes that the decision to pursue LEED Certification would have been more appropriately made at the commencement of design, the team is proud of the many green features of the project and has chosen to seek LEED Certification at this time. Because the fundamental building systems commissioning process will begin after construction has started, the project team is suggesting the following alternate compliance path for the prerequisite. The team asks the USGBC to review the commissioning strategy outlined below and to advise on whether this approach fully meets the requirements of EA Prerequisite 1: 1. Designate an individual as the CxA: The Owner has designated an employee of the HVAC, design-build sub-contractor as the CxA. The selected individual for this role has not been involved with the design or construction of the project. He has served as the commissioning agent for several projects of similar scope and technical complexity and is a certified Testing, Adjusting and Balancing Bureau (TABB) Supervisor. 2. CxA shall review Owner\'s Project Requirements and Basis of Design: The Design Team and Owner will prepare the Owner\'s Project Requirements to include Owner and User Requirements, Environmental and Sustainability Goals, Energy Efficiency Goals, Indoor Environmental Quality Requirements, Equipment and System Expectations, and Building Occupant and O & M Personnel Requirements. The Design Team will prepare a Basis of Design narrative which explains the design of the HVAC&R systems, the project lighting, the domestic hot water system, associated controls, and any additional systems requiring commissioning. The CxA will review and comment on these documents and the documents will be updated by the owner and design team respectively. 3. Develop and incorporate commissioning requirements into the construction documents: The construction drawings and specifications include the commissioning requirements of the Seattle Energy Code: a Commissioning Plan, Systems Testing and Balancing, Equipment Functional Performance Testing, Controls Functional Performance Testing, a Preliminary Commissioning Report, Post Construction Documentation, and a Final Commissioning Report. The CxA will review the commissioning requirements outlined in the construction documents and if he finds that enhancements or additions are required, these changes will be issued as supplemental instructions to the construction team and will become part of the construction documents. 4. Develop and implement commissioning plan: The CxA will review the commissioning plan outlined in the construction documents and will use this as the basis for his project commissioning plan which will include the Commissioning Program Overview, the Commissioning Team, and the Description of the Commissioning Process Activities. 5. Verify installation and performance of systems to be commissioned and complete a commissioning report: Because the systems have not been installed, the CxA will follow the credit requirements outlined in the LEED-NC v2.2 reference guide for these two steps in the commissioning process.

Ruling:

The inquiry is asking if a project that is under a "fast track" schedule and is in the early stages of construction can still comply with the requirements for fundamental commissioning. The inquiry states that since the project is already under construction a modified plan will be implemented. 1. Yes, the individual described in the above inquiry is acceptable to meet the requirement of the prerequisite, as noted in the prerequisite language and in the document posted on the USGBC website, entitled "Who Can Be the Commissioning Authority" (https://www.usgbc.org/ShowFile.aspx?DocumentID=1262). 2. The inquiry indicates that, although the OPR and BOD documentation have not been developed, the design team and owner will prepare these documents for review and comment by the CxA as required. The CxA will review these documents and will issue recommendations for enhancements and/or modifications to the design. If these design modifications are accepted by the owner, the design team will issue supplemental instruction to the project team that will become a part of the construction documents. Although the preparation and review of the OPR and BOD documents is intended to be handled during the design phase when modifications to the design can reasonably be made, the project team has outlined a plan, to incorporate any approved system modifications and/or enhancements into the project as changes to the construction process, that appears to meet the intent of the prerequisite. 3. The inquiry indicates that the basic fundamental commissioning tasks were incorporated into the construction documents prior to construction. The CxA will review these tasks and will provide the design team with any modifications required to comply with this prerequisite. Provided the team can substantiate that the appropriate tasks were included in the amended construction documents, and that the noted tasks were carried out, it appears that this portion of the prerequisite\'s intent will be satisfied. 4. The inquiry indicates that a commissioning plan was incorporated into the construction documents prior to construction. The CxA will review the plan and will provide any modifications required to comply with this prerequisite. Provided the team can substantiate that the commissioning plan includes all of the required prerequisite task elements, this portion of the prerequisite\'s intent and requirements will be satisfied 5. The inquiry indicates that the installation and performance of the installed systems to be commissioned will be verified by the CxA. The inquiry also states that the required commissioning report will be completed. The overall plan, as indicated in the above inquiry, appears to meet the intent and requirements of the prerequisite. As prerequisites cannot be awarded in the CIR process, the project team will need to provide appropriate documentation in the project\'s submittal package to confirm that the stated tasks and elements have been successfully incorporated and implemented. Applicable Internationally.

Campus Applicable
No
Internationally Applicable:
Yes
1/23/2009
LEED Interpretation
Inquiry:

Our client is a non-profit trade association which has leased space in a commercial office building in Washington, DC for 35 years. As part of an additional 10-year lease renewal and expansion, their interior space has been undergoing renovation. Upgrades to 124,000 of the 141, 000 square feet that the tenant occupies were completed in 2006 using a green approach. 10,000 square feet is currently being constructed, and 7,000 square feet is currently in design. The tenant occupies approximately 55% of the building in which they are located. Since the renovation began, the association has come to recognize LEED as an important performance benchmark of green building quality. The association is pursuing certification for its space in order to demonstrate the value of LEED CI certification to its employees and to educate its approximately 8000 corporate member organizations nationwide about LEED. The association\'s hope is to certify all 141,000 square feet of the space that they occupy. The association could limit the LEED CI site boundary to the 10,000 square feet that is currently under construction and the 7,000 square feet in which construction has not yet begun, and meet all LEED CI prerequisites and sufficient credit points to certify that portion of their space at a Silver or Gold level. They are interested, however, to undergo the additional effort and expense associated with including the 124,000 square feet of space that was renovated in earlier phase of renovation. We have confirmed that sufficient credit points could be documented for the whole space to be eligible for certification, however, the issue of how the EAp1 Fundamental Building Systems Commissioning prerequisite would need to be addressed. Alternatively we considered working with the association to pursue LEED OM for their entire space, however, LEED OM presents its own set of challenging issues given its current whole building approach and the fact that the association does not have direct control over the base building components or the activities of other building tenants. In order to include the previous phase of interior renovation in the LEED CI site boundary, we propose adapting LEED OM EAc1 requirements for commissioning the energy related systems in the tenant\'s scope whereby we would: 1. Develop a retro-commissioning, recommissioning or ongoing commissioning plan for the tenant\'s scope energy related systems, including the heating, ventilating, air conditioning and refrigeration (HVAC&R) systems and associated controls, lighting controls, including daylighting, domestic hot water systems, and renewable energy systems. 2. Conduct the investigation and analysis phase. Document the breakdown of energy use in the tenant space. 3. List the operating problems that affect occupants\' comfort and energy use, and develop potential operational changes that will solve them. 4. List the identified capital improvements that will provide cost-effective energy savings and document the cost-benefit analysis associated with each. Please let us know if this would be an acceptable alternate approach to meeting the LEED CI EAp1 Fundamental Commissioning prerequisite for the phases of the renovation already completed. The current and future phases of the project would follow the standard LEED CI EAp1 requirements.

Ruling:

The applicant is requesting approval for commissioning of spaces that have both begun construction and have completed the construction phase. Commissioning for portions of the building that have begun construction (i.e., 10,000 square feet) are eligible to achieve certification for EAp1 per a LEED-NC v2.2 CIR dated 9/18/2007 and a LEED-NC v2.1 CIR dated 2/5/2004. Projects that have already been completed, however, are ineligible to achieve LEED certification because the fundamental commissioning requirements in EAp1 were not addressed during the project design or construction phase. For portions of the building that have not been installed, the project team should develop Owners Project Requirements (OPR) and Basis of Design (BOD) documents as outlined in the LEED-CI v2.0 Reference Guide. Refer the CIR dated 9/18/2007 for additional information. All of the additional commissioning requirements outlined in the LEED-CI v2.0 Reference Guide must be satisfied. For portions of the building for which construction has been partially completed, the CxA must review not only the construction/installation of the commissioned systems but also whether the systems satisfy the design intent. Refer to the CIR dated 2/5/2004 for additional information regarding commissioning of partially installed systems and commissioning requirements. While the project team should be commended for the sustainable design practices implemented for portions of the building that have completed construction, these spaces are not eligible to achieve certification for LEED-CI. As identified in the request above, the project team should consider certifying completed portions of the building using LEED-EB. The owner may be able to convince the building association and/or other tenants to consider certifying the entire building using LEED-EB. Applicable Internationally.

Campus Applicable
No
Internationally Applicable:
Yes
2/9/2009
LEED Interpretation
Inquiry:

The purpose of this credit interpretation request is to confirm that the qualifications of the person the Owner has selected to complete Fundamental Commissioning for the project are acceptable. The project is a 150,000 SF speculative office building, with the Owner serving as the General Contractor for construction.. The project will complete the Fundamental Commissioning requirements (EAp1) but will not pursue Enhanced Commissioning (EA 3). The Owner has selected an individual employed by an independent company (not employed by the Owner/ General Contractor\'s firm) to perform commissioning for the building. The requirements specified in EA p1 for the commissioning agent state that "the CxA shall have documented commissioning authority experience in at least two projects". The selected commissioning agent has not commissioned a LEED project before but has served on numerous existing building projects overseeing the replacement of major system. He has also worked with at least two new building projects, where he was responsible for oversight during the installations of building systems. His responsibilities included: - review of plans before initial construction - meetings with sub-contractors to clarify requirements - attending relevant construction meetings - site visits for start-up of all major mechanical components - reviewing initial start-ups and making recommendations to ensure systems were working as specified - reviewing final test results and reports and making recommendations to avoid foreseeable problems suggested by the reports - coordinating with contractors and building engineers to make all warranty and non-warrantee repairs. Documentation prepared for these projects is comprised of a report outlining: - design phase drawing comments for major building systems - results of site visits to confirm that suggested changes were included in construction to witness system start-ups - a chronicle of post-construction follow-up which included witnessing of building system training for building staff. Please confirm that this individual\'s project experience is sufficient to meet the requirements for him to serve as the commissioning agent for EAp1.

Ruling:

The applicant is requesting confirmation that the selected commissioning authority (CxA) satisfies the commissioning qualifications outlined in the LEED-CS v2.0 Reference Guide. The CIR states that the selected commissioning agent is independent of the project\'s design and construction management teams and has documented CxA experience on several projects. The selected CxA is not required to have commissioning experience specifically related to LEED projects and, therefore, appears to meet the qualifications outlined in the reference guide. However, sufficient documentation must demonstrate commissioning of the two non-LEED projects through issues, logs and/or Cx checklists for all energy systems. Please note that the favorable ruling of this CIR does not guarantee credit acceptance during a review. Applicable Internationally.

Campus Applicable
No
Internationally Applicable:
Yes
9/18/2007
LEED Interpretation
Inquiry:

The owner is utilizing design/ build firms for the mechanical and electrical systems on this project. The mechanical firm has in-house design, construction, automation and commissioning services. The mechanical firm has a very clear separation of these four functions with separate management over each, so our clarification is to confirm that the mechanical firm can provide commissioning services for this prerequisite (we are NOT asking for EA3, Enhanced Commissioning). Each of these four functions have indepenent managers within the firm who answer directly to the president. The CxA for the mechanical firm will not be the Engineer-of-Record, nor will he have any construction or design responsibilities, other than as required in the CxA role (to review and verify design and construction processes, submittals and installations). His sole role and responsibility will be the proper commissioning of the project such that it meets the Owner\'s Project Requirements, the Basis of Design and the overall intent and expectation of the Owner. Our CxA meets all of the requirements for this prerequisite and has been approved by the Owner and Architect to provide this service. As described in the prerequisite\'s section, our CxA: 1. has experience on multiple projects of similar managerial and technical complexity. 2. will be independent of the design and construction teams as described above. 3. will not have responsibility for design (not the Engineer-of-Record) or for construction. 4. will report his results, findings and recommendations directly to the Owner Is this structure and our selected CxA acceptable to meet the requirement as defined in the prerequisite?

Ruling:

The project team is inquiring if a member of the mechanical design/build firm, who is not associated with the actual design or construction of the project, can be used as the commissioning agent under the requirements of the Fundamental Commissioning prerequisite (EAp1). As noted in the in the prerequisite language and in a document posted on the USGBC website, entitled "Who Can Be the Commissioning Authority" (https://www.usgbc.org/ShowFile.aspx?DocumentID=1262), the individual serving as the Commissioning Authority may be an employee or subcontractor of the A/E and/or Construction firm(s) provided they have no project responsibilities other than commissioning. As such, the individual described in the above inquiry is acceptable to meet the requirement of the prerequisite. Applicable Internationally.

Campus Applicable
No
Internationally Applicable:
Yes
5/9/2011
LEED Interpretation
Inquiry:

Can an individual who has not been a CxA in the past, but has extensive experience with all aspects of the commissioning process, serve as the CxA for a LEED project?

Ruling:

To meet the requirements of EAp1, the individual serving as the CxA must have commissioning experience at a similar managerial level on a minimum of two projects of comparable complexity. While this experience is typically confirmed based on previous experience as the CxA, it can be achieved based on similar experience. Applicable internationally.

Campus Applicable
No
Internationally Applicable:
Yes
6/27/2008
LEED Interpretation
Inquiry:

This CIR is seeking clarification on the scope of Systems Performance Testing required for Commissioning. The project is a 300,000 square foot residential building located in New York City. As part of commissioning, the project intends to commission the HVAC and refrigeration systems, lighting and daylighting controls and domestic hot water systems as per the credit requirements of EA prerequisite 1 and EA credit 3. All major equipment in the building will be commissioned such as boilers, hot water pumps, roof top units (DX), supply and exhaust fans. However, for cooling, the residences use Packaged Terminal Air Conditioners (PTAC). The Project is seeking guidance on the representative sampling of PTAC for the systems performance testing. The project is intending to test 10% (industry standard) of the PTACs in the building for each size (7500 Btu, 9000 Btu, 12000 Btu etc.) subject to a minimum count of 10. For example, if there are 27 units of Type A, and 120 units of Type B and 400 units of Type C, the functional testing will be done for: 10 qty - Type A 12 qty - Type B 40 qty - Type C If failures are found in a group, in addition to the faulty units, an additional sample is tested. Is this approach of a 1 in 10 representative sampling acceptable to USGBC?

Ruling:

Yes, in this specific case, 10% of PTAC systems subject to a minimum count of 10 are acceptable representative sampling for the systems performance testing. However, in a large multi-family residential project, the operation of a PTAC system may be influenced by the location/orientation of the residential unit. Since, it is being proposed that only representative samples would be tested, therefore, the project team should be careful in the selection of the representative samples and provide sufficient documentation when submitting for LEED review.

Campus Applicable
No
Internationally Applicable:
No
4/23/2008
LEED Interpretation
Inquiry:

In this CIR, we are asking for a clarification on whether this firm meets the experience requirements for it to provide CxA services on the project described below for its compliance with the LEED prerequisite, which requires that the CxA shall have commissioning authority experience on at least two building projects. The project to be commissioned is a proposed 3,000 Sf (+-) Bath House facility at a Town owner Pool/Park complex in New York. The Bath House building has no HVAC system, except for an exhaust fan system. Its construction will require the demolition of an existing building. Our firm has 49 years of design, construction and startup phase experience on numerous projects having similar or larger managerial and technical complexities required for the Bath House. Our firm has provided construction management (CM) services for various NY State, County and municipal projects in New York. Those services include design review and oversight, LEED review and oversight, constructability reviews and value engineering reviews, prepare and review cost estimates, assuring contractor complies with design intent and construction contract documents, work progress inspection and monitoring, quality assurance and start-up system testing, commissioning and commissioning oversight, post construction monitoring, construction trades employers, etc. Our recent experience includes such services for Suffolk County, New York\'s proposed LEED certified, $15 million, 36,000 SF Police Precinct building; the $35 million, 72,000 SF Trump On The Ocean Catering Facility, at Jones Beach, NY (also pursuing LEED certification); the Town of Hempstead, $5 million Hewlett Point Park Pool Complex; the $35 million, 200,000 SF renovation and addition of the Riverhead, NY Supreme Court building; the $55 million, 260,000 SF DASNY Health Technology Center, in Brentwood, NY; the $25 million, 150,000 SF Skilled Nursing Home Facility, in Yaphank, NY, and the new $140 million Correctional Facility in Yaphank, NY, among others. Our firm also provides engineering and architectural design services. Design services include site, building, energy, HVAC and controls systems, etc. Our staff includes professional Mechanical, Electrical, Civil and Structural Engineers, Registered Architects and LEED Accredited Professionals. Our personnel have extensive experience in energy systems design, installation, performance and operation. We also perform on-site, hands on inspections of the energy systems including start-up, testing balancing, troubleshooting, operation, and maintenance procedures. In this specific case, our firm is not involved in the design or construction management phases of this LEED registered project. As the CxA, our firm will review and verify design and monitor construction and will perform the requirements of the Fundamental Commissioning of the Building Energy Systems.

Ruling:

Assuming your firm provided commissioning services on at least 2 of the projects listed, you qualify to serve as the CxA for the bath house project. Your description indicates that you are not part of the design or construction team, and you list multiple relevant projects, thus the eligibility requirements are satisfied. Applicable Internationally.

Campus Applicable
No
Internationally Applicable:
Yes
See all forum discussions about this credit »

Checklists

Step by step to LEED certification

LEEDuser’s checklists walk you through the key action steps you need to earn a credit, including how to avoid common pitfalls and save money.

See all forum discussions about this credit »

Documentation toolkit

The motherlode of cheat sheets

LEEDuser’s Documentation Toolkit is loaded with calculators to help assess credit compliance, tracking spreadsheets for materials, sample templates to help guide your narratives and LEED Online submissions, and examples of actual submissions from certified LEED projects for you to check your work against. To get your plaque, start with the right toolkit.

Credit achievement rate

XX%

Upgrade to LEEDuser Premium to see how many projects achieved this credit. Try it free »

LEEDuser expert

Scott Bowman

Integrated Design + Energy Advisors, LLC
LEED Fellow

Get the inside scoop

Our editors have written a detailed analysis of nearly every LEED credit, and LEEDuser premium members get full access. We’ll tell you whether the credit is easy to accomplish or better left alone, and we provide insider tips on how to document it successfully.

USGBC logo

© Copyright U.S. Green Building Council, Inc. All rights reserved.

Requirements

The following commissioning process activities must be completed by the project team:

  • Designate an individual as the commissioning authority (CxA) to lead, review and oversee the completion of the commissioning process activities.
    • The CxA must have documented commissioning authority experience in at least 2 building projects.
    • The individual serving as the CxA must be independent of the project’s design and construction management, though the CxA may be an employee of any firms providing those services. The CxA may be a qualified employee or consultant of the owner.
    • The CxA must report results, findings and recommendations directly to the owner.
    • For projects smaller than 50,000 gross square feet (4,500 gross square meters), the CxA may be a qualified person on the design or construction teams who has the required experience.
  • The owner must document the owner’s project requirements. The design team must develop the basis of design. The CxA must review these documents for clarity and completeness. The owner and design team must be responsible for updates to their respective documents.
  • Develop and incorporate commissioning requirements into the construction documents.
  • Develop and implement a commissioning plan.
  • Verify the installation and performance of the systems to be commissioned.
  • Complete a summary commissioning report.
Commissioned Systems
Commissioning process activities must be completed for the following energy-related systems, at a minimum (if they are installed as part of the core and shell project):
  • Heating, ventilating, air conditioning and refrigeration (HVAC&R) systems (mechanical and passive) and associated controls.
  • Lighting and daylighting controls.
  • Domestic hot water systems.
  • Renewable energy systems (e.g. wind, solar).
Credit substitution available
You may use the LEED v4 version of this credit on v2009 projects. For more information check out this article.

XX%

Upgrade to LEEDuser Premium to see how many projects achieved this credit. Try it free »

Got the gist of EAp1 but not sure how to actually achieve it? LEEDuser gives step-by-step help. Premium members get:

  • Checklists covering all the key action steps you'll need to earn the credit.
  • Hot tips to give you shortcuts and avoid pitfalls.
  • Cost tips to assess what a credit will actually cost, and how to make it affordable.
  • Ideas for going beyond LEED with best practices.
  • All checklists organized by project phase.
  • On-the-fly suggestions of useful items from the Documentation Toolkit and Credit Language.

In the end, LEED is all about documentation. LEEDuser’s Documentation Toolkit, for premium members only, saves you time and helps you avoid mistakes with:

  • Calculators to help assess credit compliance.
  • Tracking spreadsheets for materials purchases.
  • Spreadsheets and forms to give to subs and other team members.
  • Guidance documents on arcane LEED issues.
  • Sample templates to help guide your narratives and LEED Online submissions.
  • Examples of actual submissions from certified LEED projects.

LEEDuser expert

Scott Bowman

Integrated Design + Energy Advisors, LLC
LEED Fellow

See all LEEDuser forum discussions about this credit » Unsubscribe from discussions about CS-2009 EAp1