LEED Online submission language

NC-v4 IPc1:Integrative process
posted by  Marcelo Alencar Pereira  on 
Can I submit projects, documents, technical sheets, and other files on the LEED Online platform in Portuguese/BR, or do I need to translate them into English?
1
Tue Jul 23, 2024, 4:16 pm

Process water

NC-v4 IPc1:Integrative process
posted by  Geetha J  on 

Hi everyone,

Should we consider the cooling tower makeup water as  process water demand?

1
Fri Oct 13, 2023, 2:25 pm
2
LEEDuser Basic Member
8 thumbs up
Tue Oct 10, 2023, 11:31 am
2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4461 thumbs up
Tue Jun 27, 2023, 4:08 pm

IP Worksheet - Very confusing language

NC-v4 IPc1:Integrative process
posted by  Maria Grimm  on 

I'm working on a project where we completed a very thorough IP analysis during concept design.

8
Default Avatar
President
Facility Performance Associates
LEEDuser Basic Member
0 thumbs up
Mon May 22, 2023, 6:20 pm
2
Practice Leader - Sustainability
EUA
LEEDuser Expert
510 thumbs up
Fri Sep 2, 2022, 1:37 pm

Certification time

NC-v4 IPc1:Integrative process
posted by  Helena Garcia   on 

Hi everyone,

Does anyone know if there is a time limit or a deadline from when a project is registered until certification is achieved?

 

Thank you in advance.

8
Wed Nov 24, 2021, 11:31 am

Pre-selected sites, can a project still opt for Integrative Process credit?

NC-v4 IPc1:Integrative process
posted by  Nermin Hegazy  on 

We are studying the feasibility of acheiving LEED certification for a series of floors in an office building.

4
Practice Leader - Sustainability
EUA
LEEDuser Expert
510 thumbs up
Wed Jun 23, 2021, 4:40 pm

Project relocated to a new site

NC-v4 IPc1:Integrative process
posted by  Sara Goenner Curlee  on 

I have a project that just completed the IP credit requirements before the end of SD, and now finds itself likely needing to relocate to a different site. The proposed new site is about 1

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4461 thumbs up
Wed Nov 4, 2020, 7:21 pm

Integrative process phase

NC-v4 IPc1:Integrative process
posted by  Marion THIBAULT  on 

Hello,
My client wishes to have his project certified in LEED V4.

4
Tue Feb 25, 2020, 2:00 pm

Simple box model

NC-v4 IPc1:Integrative process
posted by  Edgar Arevalo  on 

Ok.... So I'm working on my first LEED v4 BD+C project, and we're looking to pursue the IP credit.

13
Sustainable Design Lead
CannonDesign
LEEDuser Expert
379 thumbs up
Fri Oct 11, 2019, 10:08 am
3
President
C-Wise Design and Consulting
LEEDuser Premium Member
70 thumbs up
Mon Sep 16, 2019, 2:38 pm

Inconsistent expectations

NC-v4 IPc1:Integrative process
posted by  Martha Norbeck  on 

To the USGBC staff who I know read these comments, please issue consistent guidance for how this credit will be evaluated. I've submitted twice for this credit.

2
Sun Sep 15, 2019, 4:04 pm

Integrative process charrette and ANSI book

NC-v4 IPc1:Integrative process
posted by  Kavita K  on 

Hi all,

We are pursuing a LEED for Schools project and are looking to get the Integrative process credit. Couple of clarifying questions -

1
Mon May 20, 2019, 9:19 pm

Water-Budget Analysis

NC-v4 IPc1:Integrative process
posted by  Summer Minchew  on 

USGBC references the Indoor and Outdoor Water Reduction Calculators; any recommendations about additional tools a team should utilize in completing their water-budget analysis?

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4461 thumbs up
Wed May 1, 2019, 7:09 pm

OPR and BOD

NC-v4 IPc1:Integrative process
posted by  Nolberto Lopez  on 

Hi. I am studying for my LEED Green Associate exam based on LEED V4. Can someone tell me in which site I could get an example of OPR and BOD for rating system NC? Thanks.

8
Mechanical Designer
Integral Group
LEEDuser Basic Member
13 thumbs up
Tue Mar 26, 2019, 10:02 am

CS-v4 IPc1 - Integrative Process (Design Charrette)

NC-v4 IPc1:Integrative process
posted by  Estra Marku  on 

I was wondering if anyone can shed some light on whether it would be acceptable to conduct a Design Charrette over the course of 4 days, as opposed to a 4 hour charrette in one day?

4
Founder & Community Director
Metricorps
LEEDuser Expert
7781 thumbs up
Tue Oct 16, 2018, 10:15 pm

Thermal Comfort Ranges

NC-v4 IPc1:Integrative process
posted by  Danilo Ilic  on 

The part "Assess Thermal Comfort Ranges" is not very clear for me.

1
Tue Oct 16, 2018, 5:32 pm

What are the main topics in construction documents that should include LEED requirements ?

NC-v4 IPc1:Integrative process
posted by  Amine Zeidane  on 

Hello,

Is there a document out there to assist in what should be written in construction documents tenders destined for the Construction and MEP companies ?

Thank you

1
Wed Sep 19, 2018, 1:39 pm

What about Site Selection?

NC-v4 IPc1:Integrative process
posted by  Michelle Rosenberger  on 

Hi Marcus, So I'm confused. LEEDuser's preamble above indicates any project can get this credit, and you're not required to implement anything just analyze.

3
Default Avatar
architect
LEEDuser Basic Member
5 thumbs up
Mon Jul 9, 2018, 1:39 pm

HVAC System Selection

NC-v4 IPc1:Integrative process
posted by  Dave Hubka  on 

It doesn't seem like the credit requires evaluation of various HVAC systems (e.g. radiant heat vs forced air heat, packaged cooling vs split systems, etc.).

3
Practice Leader - Sustainability
EUA
LEEDuser Expert
510 thumbs up
Thu May 10, 2018, 2:21 pm

FAO EToCalc software help

NC-v4 IPc1:Integrative process
posted by  S. Sachs  on 

Hello, I'm working on a project in Kuwait and need to achieve the IPc1 credit for water consumption. I've been struggling to use the LEED-recommended ETo calculator tool, produced by the FAO, whi

1
Thu Oct 18, 2018, 7:32 pm

Can I omit the IP credit since it is stand alone?

NC-v4 IPc1:Integrative process
posted by  wachira sosaeng  on 

Generally,in other categories, we have to perform to meet all prerequisites though we don't need any credits in the categories (suppose that we have enough credits that meet our goal.

1
Mon Aug 1, 2016, 3:21 pm

Adoption of Investigated Strategies

NC-v4 IPc1:Integrative process
posted by  Philippa Cameron  on 

Do you need to adopt all strategies that you demonstrate as facilitating best energy performance for this credit?

1
Wed Oct 28, 2015, 3:31 pm

simple box model

NC-v4 IPc1:Integrative process
posted by  Courtney Royal  on 

how do you define a simple box model? for example, do you need to model thermal zones, etc.

1
Wed Apr 26, 2017, 2:01 pm

Design Build Projects

NC-v4 IPc1:Integrative process
posted by  Michelle Rosenberger  on 

Our region primarily uses design build which means that there are two very separate Schematic Design processes for our projects.

4
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4461 thumbs up
Wed May 3, 2017, 4:58 pm

Energy-related systems

NC-v4 IPc1:Integrative process
posted by  Lise Dannesboe  on 

Hi! We did some parameter studies in the early stage of the design process. Now i am wondering if we can use them for documentation of this credit.

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4461 thumbs up
Mon Aug 15, 2016, 7:02 am

Integrative Process (IP) Guide 2.0

NC-v4 IPc1:Integrative process
posted by  Vitor Tosetto   on 

Please, someone knows where can I buy the Integrative Process (IP) ANSI Consensus National Standard Guide© 2.0? In ANSI's webstore I found v1.0 only.

10
Thu Aug 4, 2016, 3:37 pm

Must non-potable water sources be used to earn IP credit?

NC-v4 IPc1:Integrative process
posted by  Eesmyal Santos-Brault  on 

It appears that this credit can not be earned if a project does not meet some water demand through nonpotable sources.

7
Mon Aug 17, 2015, 8:02 pm

Charrette duration / delivery flexible?

NC-v4 IPc1:Integrative process
posted by  Vince Briones  on 

Has anyone had success with (2) 2-hr sessions being accepted as compliant (by GBCI) for the integrated design team charrette?

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4461 thumbs up
Fri Feb 20, 2015, 7:47 pm

Prerequisite

NC-v4 IPc1:Integrative process
posted by  Lorne Mlotek  on 

Just want confirmation that there is no prereq for performing IP.

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4461 thumbs up
Tue Jun 10, 2014, 2:30 pm