LEED Online submission language
NC-v4 IPc1:Integrative processposted by Marcelo Alencar Pereira on
Process water
NC-v4 IPc1:Integrative processposted by Geetha J on
Hi everyone,
Should we consider the cooling tower makeup water as process water demand?
how can attachments (drawings, images) be sent in a CIR?
NC-v4 IPc1:Integrative processposted by Sara BENLOUBA on
Dear Everybody,
How contact GBCI for their advice on technical matters
NC-v4 IPc1:Integrative processposted by Sara BENLOUBA on
Dear everybody,
IP Worksheet - Very confusing language
NC-v4 IPc1:Integrative processposted by Maria Grimm on
I'm working on a project where we completed a very thorough IP analysis during concept design.
GFA calculation for extremely thick walls
NC-v4 IPc1:Integrative processposted by Filippo Weber on
Hi,
Certification time
NC-v4 IPc1:Integrative processposted by Helena Garcia on
Hi everyone,
Does anyone know if there is a time limit or a deadline from when a project is registered until certification is achieved?
Thank you in advance.
Pre-selected sites, can a project still opt for Integrative Process credit?
NC-v4 IPc1:Integrative processposted by Nermin Hegazy on
We are studying the feasibility of acheiving LEED certification for a series of floors in an office building.
Project relocated to a new site
NC-v4 IPc1:Integrative processposted by Sara Goenner Curlee on
I have a project that just completed the IP credit requirements before the end of SD, and now finds itself likely needing to relocate to a different site. The proposed new site is about 1
Integrative process phase
NC-v4 IPc1:Integrative processposted by Marion THIBAULT on
Hello,
My client wishes to have his project certified in LEED V4.
Simple box model
NC-v4 IPc1:Integrative processposted by Edgar Arevalo on
Ok.... So I'm working on my first LEED v4 BD+C project, and we're looking to pursue the IP credit.
When exactly to submit for this credit?
NC-v4 IPc1:Integrative processposted by Sayali G on
Hey All,
Inconsistent expectations
NC-v4 IPc1:Integrative processposted by Martha Norbeck on
To the USGBC staff who I know read these comments, please issue consistent guidance for how this credit will be evaluated. I've submitted twice for this credit.
Integrative process charrette and ANSI book
NC-v4 IPc1:Integrative processposted by Kavita K on
Hi all,
We are pursuing a LEED for Schools project and are looking to get the Integrative process credit. Couple of clarifying questions -
Water-Budget Analysis
NC-v4 IPc1:Integrative processposted by Summer Minchew on
USGBC references the Indoor and Outdoor Water Reduction Calculators; any recommendations about additional tools a team should utilize in completing their water-budget analysis?
OPR and BOD
NC-v4 IPc1:Integrative processposted by Nolberto Lopez on
Hi. I am studying for my LEED Green Associate exam based on LEED V4. Can someone tell me in which site I could get an example of OPR and BOD for rating system NC? Thanks.
CS-v4 IPc1 - Integrative Process (Design Charrette)
NC-v4 IPc1:Integrative processposted by Estra Marku on
I was wondering if anyone can shed some light on whether it would be acceptable to conduct a Design Charrette over the course of 4 days, as opposed to a 4 hour charrette in one day?
Thermal Comfort Ranges
NC-v4 IPc1:Integrative processposted by Danilo Ilic on
The part "Assess Thermal Comfort Ranges" is not very clear for me.
What are the main topics in construction documents that should include LEED requirements ?
NC-v4 IPc1:Integrative processposted by Amine Zeidane on
Hello,
Is there a document out there to assist in what should be written in construction documents tenders destined for the Construction and MEP companies ?
Thank you
What about Site Selection?
NC-v4 IPc1:Integrative processposted by Michelle Rosenberger on
Hi Marcus, So I'm confused. LEEDuser's preamble above indicates any project can get this credit, and you're not required to implement anything just analyze.
HVAC System Selection
NC-v4 IPc1:Integrative processposted by Dave Hubka on
It doesn't seem like the credit requires evaluation of various HVAC systems (e.g. radiant heat vs forced air heat, packaged cooling vs split systems, etc.).
FAO EToCalc software help
NC-v4 IPc1:Integrative processposted by S. Sachs on
Hello, I'm working on a project in Kuwait and need to achieve the IPc1 credit for water consumption. I've been struggling to use the LEED-recommended ETo calculator tool, produced by the FAO, whi
Can I omit the IP credit since it is stand alone?
NC-v4 IPc1:Integrative processposted by wachira sosaeng on
Generally,in other categories, we have to perform to meet all prerequisites though we don't need any credits in the categories (suppose that we have enough credits that meet our goal.
Adoption of Investigated Strategies
NC-v4 IPc1:Integrative processposted by Philippa Cameron on
Do you need to adopt all strategies that you demonstrate as facilitating best energy performance for this credit?
simple box model
NC-v4 IPc1:Integrative processposted by Courtney Royal on
how do you define a simple box model? for example, do you need to model thermal zones, etc.
Design Build Projects
NC-v4 IPc1:Integrative processposted by Michelle Rosenberger on
Our region primarily uses design build which means that there are two very separate Schematic Design processes for our projects.
Energy-related systems
NC-v4 IPc1:Integrative processposted by Lise Dannesboe on
Hi! We did some parameter studies in the early stage of the design process. Now i am wondering if we can use them for documentation of this credit.
Integrative Process (IP) Guide 2.0
NC-v4 IPc1:Integrative processposted by Vitor Tosetto on
Please, someone knows where can I buy the Integrative Process (IP) ANSI Consensus National Standard Guide© 2.0? In ANSI's webstore I found v1.0 only.
Must non-potable water sources be used to earn IP credit?
NC-v4 IPc1:Integrative processposted by Eesmyal Santos-Brault on
It appears that this credit can not be earned if a project does not meet some water demand through nonpotable sources.
Charrette duration / delivery flexible?
NC-v4 IPc1:Integrative processposted by Vince Briones on
Has anyone had success with (2) 2-hr sessions being accepted as compliant (by GBCI) for the integrated design team charrette?
Prerequisite
NC-v4 IPc1:Integrative processposted by Lorne Mlotek on
Just want confirmation that there is no prereq for performing IP.