RCI Visual Inspections- STILL???

NC-v4.1 MRc5: Construction and demolition waste management
posted by Kimberlee Ilardi on Oct 7, 2019, 3:04 pm

Tiffany Beffel Managing Partner Innovative Workshop Consulting LEEDuser Expert 22 thumbs up October 21, 2019- 6:20 am Hi Kimberlee!  This is a hot topic for sure and I want to direct you to MRc2, where there was some key discussion with regard to visual inspections:  https://leeduser.buildinggreen.com/forum/alternative-calculation-mrc2.  You are correct, commingled is considered single-stream, whether it is project specific or the facility average.  And, it still remains true that visual inspection is not an acceptable method of evaluation. I am curious how their visual inspection effects...

Last reply: Tiffany Beffel, Nov 15, 2019, 2:56 pm

Commingled waste and numbers of waste streams

NC-v4.1 MRc5: Construction and demolition waste management
posted by Bryna Dunn on Apr 9, 2020, 4:59 pm

Is there a documented environmental benefit to all the extra red tape we have to wade through "for LEED points" for projects where collecting in a commingled bin is actually the most likely way...

Last reply: Tiffany Beffel, May 31, 2020, 2:00 pm

Option 2- Reduction of Total Waste Material for major renovation project

NC-v4.1 MRc5: Construction and demolition waste management
posted by Adam Yarnell on May 6, 2020, 3:51 pm

Hi,

What is everyone's take on pursuing Option 2 for a major renovation project? A hopeful approach is to target a 75% diversion for the demo and...

Last reply: Tiffany Beffel, May 31, 2020, 2:32 pm

LEED v4.1 Construction Waste Calculator

NC-v4.1 MRc5: Construction and demolition waste management
posted by Mary Lea Tucker on Jun 26, 2020, 7:35 pm

Are the point amounts listed in the summary of the calculator incorrect? They don't seem to match the 4.1 guide. Did I miss an update?

Calculator -
Option 1 Credit Pathways:
...

Exemplary Performance

NC-v4.1 MRc5: Construction and demolition waste management
posted by Maria Porter on Oct 8, 2020, 5:44 am

EP seems to be removed in v4.1, correct? In v4 it was take both option 1 and 2.

Last reply: Maria Porter, Oct 8, 2020, 8:17 am

v4.1 MRc5 option 2 with MRpc87

NC-v4.1 MRc5: Construction and demolition waste management
posted by Kyle Roth on Apr 21, 2021, 11:41 am

Can you use the pilot credit Verified Construction & Demolition Recycling Rates with the v4.1 Construction and Demolition Waste Management credit, option 2?

ID# 100002448

NC-v4.1 MRc5: Construction and demolition waste management
posted by Esther Leung on Nov 30, 2020, 8:35 am

Under the latest Addenda issued November 9, 2020 (https://www.usgbc.org/leedaddenda/100002448), do you agree that the requirements on ...

Last reply: Sarah Buffaloe, May 19, 2021, 9:19 am

November Surprise?

NC-v4.1 MRc5: Construction and demolition waste management
posted by Jonathan Weiss on Nov 24, 2020, 3:41 pm

I am hoping I read this wrong, but the current version of the credit on USGBC.org and the Addendum posting (as of early November) seems to have changed this credit significantly - Option 1 is 1...

Last reply: Chloe Bendistis, Sep 1, 2021, 12:53 pm

Commingled recycling

NC-v4.1 MRc5: Construction and demolition waste management
posted by Domenic Smart on Mar 18, 2022, 3:13 pm

Does anyone know of a facility around the Detroit Metropolatin area that does commingled recycling?

How are waste streams classified? Based on materials type? Weight? Volume?

NC-v4.1 MRc5: Construction and demolition waste management
posted by Ayman Raouf on Jul 18, 2022, 1:18 pm

The credit stipulates the below:

Divert 50% and 3 material streams for Option 1 Diversion, Path 1.

Divert 75% and 4 material streams for Option 1 Diversion, Path 2.

...