Forum
Topic | Recent |
---|---|
LEED v4.1 Renewable Energy- no contracts with a period longer than two years availableNC-v4.1 EAc5: Renewable energyposted by J Schütz on Apr 2, 2020, 10:30 am
Dear all, Actually, German law prohibits electricity contracts with a fixed contract period longer than two years, there has to be the possibility to cancel the contract. Although, the... Last reply: Hashir Usman, Mar 30, 2022, 7:44 am |
|
v4.1 Renewable Energy // heat pump in Tier1?NC-v4.1 EAc5: Renewable energyposted by Claudia Sturcz on Oct 15, 2020, 3:15 am
Dear All, According to v4.1 do heat pumps belong to Tier1 category? If the energy will be provided in equal rate from boilers and heat pumps than we shoud calculate 50% renewable? Or this... Last reply: Marcus Sheffer, Oct 15, 2020, 8:08 am |
|
Certificates for Tier 1NC-v4.1 EAc5: Renewable energyposted by Davide Liviero on Oct 28, 2020, 5:35 am
Hello everyone, is the acquisition of certificates (EECS-GO in my case) necessary also for On-site... Last reply: Marcus Sheffer, Oct 28, 2020, 9:32 am |
|
How to validate applicability of Tier 2 & 3 RECsNC-v4.1 EAc5: Renewable energyposted by Joyce Kelly on Nov 5, 2020, 12:39 pm
An organization contracts with a local utility to exclusively purchase energy from renewable sources for 20 yrs. This agreement, makes it possible for the utility to commit to more... Last reply: Marcus Sheffer, Nov 19, 2020, 1:38 pm |
|
Project Energy Use_Electric or Overall Energy use?NC-v4.1 EAc5: Renewable energyposted by Hashir Usman on Feb 23, 2021, 11:42 am
Hi, I am a bit confused about this credit. In reference guide it states ''Points are awarded according to Table 1, based on the percentage of total site energy use. Renewable electricity... Last reply: Marcus Sheffer, Mar 1, 2021, 5:16 pm |
|
TrigenerationNC-v4.1 EAc5: Renewable energyposted by Davide Liviero on Mar 1, 2021, 12:21 pm
Hello everyone, I am carrying out a preliminary analysis for a hospital. We are thinking of adding a trigeneration plant within the project. Could it be considered within the Renewable... Last reply: Marcus Sheffer, Mar 1, 2021, 2:22 pm |
|
Whic Tier of Renewable Energy for our project?NC-v4.1 EAc5: Renewable energyposted by Dang Thi on Mar 15, 2021, 12:11 am
Hi everyone, Our client decides to setup a new factory in a industrial zone. Industrial zone will let a company A to invest grid subregion. Company A set up grid, and they will hire... Last reply: Marcus Sheffer, Mar 15, 2021, 9:45 am |
|
Adding points from different Tiers?NC-v4.1 EAc5: Renewable energyposted by Kimberly Reddin on Apr 19, 2021, 3:55 pm
Hopefully this is an easy one, I just want to be sure I'm reading this credit correctly. The credit language says “points achieved in each category may be added for a total of 5 points... Last reply: Marcus Sheffer, Apr 30, 2021, 3:43 pm |
|
Ground Source Heat Pumps not Considered as Renewable Energy System by LEEDNC-v4.1 EAc5: Renewable energyposted by Ayman Raouf on Sep 9, 2021, 11:00 am
In LEED Reference guide, it states "Geothermal energy, such as electricity generated from subterranean steam or heat generated from subterranean steam or hot water, is eligible. However,... Last reply: Marcus Sheffer, Sep 10, 2021, 12:32 pm |
|
District heating form sewage sludge combustion as renewable energy?NC-v4.1 EAc5: Renewable energyposted by J Schütz on Sep 30, 2021, 5:10 am
Dear all, 40% of the district heating one of our projects procures is generated from the combustion of sewage sludge and Biogenic waste. Can this be counted as... Last reply: Marcus Sheffer, Sep 30, 2021, 1:23 pm |