EAc1.3 Option 2: Baseline vs Alternate Baseline

CI-2009 EAc1.3:Optimize Energy Performance—HVAC
posted by  Ken Williams  on 

I am working on a small building that is pursuing LEED CI. The building is comprised of two tenant spaces, office and restaurant/dining.

3
Wed Sep 10, 2014, 1:26 pm

Flooring & Composite Wood Emissions and Content Standards

NC-v4 EQc2:Low emitting materials
posted by  Ian McCall  on 

Dear All, Our project is considering using flooring made of laminated composite wood. Under "Table 1" page 658 is this building element considered as "Flooring" or "Composite wood" or both?

3
Wed Sep 10, 2014, 8:28 am

Energy Star Portfolio Manager

EBOM-2009 EAp2:Minimum Energy Efficiency Performance
posted by  Kelly Webb  on 

We are working on a multi tenant project and during our performance period the owner lost a large tenant.

5
Default Avatar
Eng., PA LEED BD+C
ENGIE Services
LEEDuser Basic Member
0 thumbs up
Tue Sep 9, 2014, 11:05 pm

System 5. Two boilers

CS-2009 EAp2:Minimum Energy Performance
posted by  Toni Herena Montull  on 

In a review, the reviewer told me that as a system type 5, I should model 2 identical boilers.

3
Tue Sep 9, 2014, 7:05 pm

6.5.3.1 Fan power limitation for a VRF + DOAS system

CI-2009 EAp2:Minimum Energy Performance
posted by  Zonda E. Team  on 

Hi there, should I consider DOAS fan power as part of the total system fan power? The DOAS transports unconditioned outside air to the mixing plenum of the VRF indoor unit. Thanks, Santiago.

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Tue Sep 9, 2014, 4:00 pm

Solar Water Heater Savings Calculation

NC-2009 EAc1:Optimize Energy Performance
posted by  Jimmy Sparkman  on 

I need to document, through LEED NC 2009, my energy savings through the use of a solar water heater. I'm not certain if there is a savings estimating spreadsheet out there for use or not.

3
Tue Sep 9, 2014, 3:21 pm

Electric meters for interior lighting and receptable loads

CS-2009 EAp2:Minimum Energy Performance
posted by  Toni Herena Montull  on 

Hi, In a Core and Shell model, for EAp2 (eQUEST), a LEED reviewer told me to define lighting and receptable loads meters.

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Tue Sep 9, 2014, 8:34 am

Switching to LEED V4

General forums
posted by  Ahmed Mosa  on 

Can we upgrade a registered LEED V3 project to be registered in LEED V4, if yes what are the steps?

3
Sustainability Consultant - Sustainable Design Researcher
P&T Architects and Engineers
LEEDuser Basic Member
8 thumbs up
Mon Sep 8, 2014, 11:52 pm

Supplemental Calculator for Residential

NC-2009 IEQc8.1:Daylight and Views—Daylight
posted by  Lauren Fakhoury  on 

I'm documenting this credit for an apartment building using the v3 supplemental daylight and views calculator.

2
Director of Sustainability
DBR Engineering Consultants
LEEDuser Basic Member
244 thumbs up
Mon Sep 8, 2014, 5:48 pm

Glass manifestation

CI-2009 IEQc4.1:Low-Emitting Materials—Adhesives and Sealants
posted by  Akos Brandecker  on 

Does anyone know if glass manifestation (decorative films on glass panels) applied on-site falls under any of the IEQ credits and if yes, what requirements it has to meet exactly? Thank you.

4
LEED-AP BD+C
GREENSQUARE
LEEDuser Expert
261 thumbs up