Existing MultiFamily High Rise-Exclude Occupied Commerical Space
Healthcare-v2009 MPR3:Must use a reasonable site boundaryposted by Laura Steinbrink on
We have an existing 13 Story Downtown Multifamily LEED NC v2009 registered project consisting of 210,000 sf and 200 units which will be gutted.
EAc1 Credits Using DES Option 1 + A lot of Renewables
NC-2009 EAp2:Minimum Energy Performanceposted by Reniel Barroso on
We have a project opting to maximize the 19points of EAc1. The project is served by a District Cooling Plant.
EAc1 points using DES Option 1 + A lot of Renewables
NC-2009 EAc1:Optimize Energy Performanceposted by Reniel Barroso on
We have a project opting to get the maximum 19 credit points in EAc1.
Energy Star Related Product
Retail-CI-v2009 EAp2:Minimum energy performanceposted by Wei Zeng on
Hello: I am working on a convenience store applying for LEED CI Retail 2009 certification, the project plans to design two outdoor air-cooled condensing unit which would be used as the cooling
n/a
Pilot-Credits SSpc55:Bird collision deterrenceposted by Maria Rios on
Hey, We are trying to prepare all documentation to get this credit, and we are having some difficulties due to the next consideration: "Plan(s) and/or elevation(s) depicting the location of all m
Commercial Interior; EAc1.3
NC-2009 EAp2:Minimum Energy Performanceposted by Vassil Vassilev on
Hi Marcus, Could you please advice me about the following situation: Regarding Option 1 of credit EAc1.3 of CI, the reviewers are requesting an extra CO2 sensor to be added for the densely occupied
Site adjacent to 5 lane highway - with no On-0ff ramp.
Warehouses-NC-v4 LTc4:Surrounding density and diverse usesposted by Joyce Kelly on
If the Distribution center is less than 1-mile driving distance of 5 lane, wide shouldered Carlyle turnpike aka Route 11 (center lane = turning lane), does that qualify as a highway for the purpo
A shared storm water tank with other projects
CS-2009 SSc6.1:Stormwater Design—Quantity Controlposted by Francesco Allaix on
I have a LEED project where they plan a storm water tank that will be a shared one with two other buildings next to the LEED project building.
Double Ridership - access to transit station
NC-2009 SSc4.1:Alternative Transportation—Public Transportation Accessposted by Erin Holdenried on
If a bus servicing your LEED project connects to a bus transfer station (within 2 miles/10 min) of the project site.
Calculating stored rainwater available
NC-2009 WEc3:Water Use Reductionposted by Yusuf Turab on
We are having some trouble coming up with the calculation for rainwater stored and reused annually.