NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Zach Hoffman on
I am wondering if IBC Group S-1 Occupancy zones are required to be tested per IEQc3.2. On this project (vehicle maintenance facility), the specific zones within the S-1 classification are maintenan
Waste stream audit
EBOM-v4 MRp1:Ongoing purchasing and waste policyposted by Michael Smithing on
We have been unable to achieve the waste stream audit credit in Hungary as waste haulage is government controlled and the waste haulers are unable (or unwilling) to provide this service.
LEED Boundary
posted by Ghaleb El Mheirat on
We are currently working on a project (Hotel) where there is a seperate utility building serving Hotel.
food contact sanitizers
EBOM-2009 IEQc3.3:Green Cleaning—Purchase of Sustainable Cleaning Products and Materialsposted by Michelle Raigosa on
Does anyone know of an approved food contact sanitizer or of a standard that certifies this type of sanitzer? Green Seal indicated they did not have one.
Changes in development program form
ND-v2009 PIf1:Development Program and Site Typeposted by Carole Frising on
I just started working on a LEED ND project for which the Masterplan has evolved after the SLL prerequisite submission.
Green-e Energy
NC-2009 EAc6:Green powerposted by PATRICK HILLIER on
We are looking at purchasing thew power for credit EAc6. 1. Can we as the A/E purchase it for the Owner? 2. How do you document the ID credit for 100% power purchased for 2 years?
Case 1 Option 2 vs. Case 2 Option 2
CI-2009 SSc3.3:Alternative Transportation—Parking Availabilityposted by Michelle Rosenberger on
Case 1 and Case 2 are distinguished by whether your CI is more than 75% of the building or not. But Option 2 reads very differently depending on which case you are.
Cx coordination with tenant move in
CS-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Matt Humphreys on
What impact will the following two situations have on earning the fundamental commissioning prerequisite? 1.
Cork tiles?
NC-2009 IEQc4.4:Low-Emitting Materials—Composite Wood and Agrifiber Productsposted by Nelina Loiselle on
We are using a cork and rubber tile flooring in part of our building. Do we need to count that under this credit because cork is an agrfiber?
Annual Maintenance Cost of White Roof
EBOM-2009 SSc7.2:Heat Island Reduction—Roofposted by Rebekah Burke on
This isn't specifically a LEED EBOM Credit question-but very pertinent as we discuss the improved performance of an exisiting building. We’re working on a project study for life-cycle costing of a