We are currently working on a project (Hotel) where there is a seperate utility building serving Hotel. The hotel is targetting LEED certificate.
I just have a small question; if the utility building serves only the hotel, shall we include it in the LEED boundary?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Tristan Roberts
RepresentativeVermont House of Representatives
LEEDuser Expert
11478 thumbs up
July 25, 2014 - 7:41 pm
Ghaleb, I would strongly consider including it. The LEED boundary should include everything essential to the project's performance. I would post this question under MPR2 and review the guidance there.