Post a question or comment
Filter by location
Forum
Topic
Replies
Recent

Documentation Required for IP Credit

Schools-NC-v4 IPc1:Integrative process
posted by  Cora Kenrick  on 

Hi Fellow LEED Users,

 

Has anyone submitted this credit yet and what documentation is required.

I'm new to LEED and this credit.

 

11
Wed Dec 11, 2019, 2:58 pm

Space Usage Calculator - Lease Type?????

CS-2009 PIf3:Occupant and Usage Data
posted by  Edgar Arevalo  on 

What does LEED/USGBC define as net and gross lease type??  I have no prior knowledge of the difference between either lease types, and yet the space usage calculator has that column which I ne

1
Fri Dec 13, 2019, 12:59 pm
3
Tue Dec 10, 2019, 4:22 pm

Unsolved adobe reader issue after following instructions

Living with LEED Online - quirks, bugs and hiccups
posted by  Nicolas Galiotto  on 

Hi there, I'm on Windows 7. Both Adobe pro and Adobe 10.1.2 were on my computer.

10
Architect
The Clark Enersen Partners
LEEDuser Basic Member
18 thumbs up
Tue Dec 10, 2019, 7:02 am
9
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Tue Dec 10, 2019, 3:10 am

Unenclosed Buildings & LEED

LEED Rating System Selection
posted by  Keith Yzquierdo  on 

What, if anything, precludes a completely unenclosed building from achieving a LEED certification? Imagine a stand-alone pavilion, band shell, or amphitheater on its own plot of land.

2
Founder & Community Director
Metricorps
LEEDuser Expert
7780 thumbs up
Tue Dec 10, 2019, 12:38 am

Timing of Installation and Commissioning

NC-v4 EAc5:Renewable energy production
posted by  Michaella Wittmann  on 

The LEED Credit template for this credit indicates that the renewable installation has to be complete and commissioned prior to building occupancy.

14
Sustainability Project Manager
Atkins
LEEDuser Basic Member
59 thumbs up
Mon Dec 9, 2019, 7:16 pm

Flush for Residential Multifamily several stories

NC-v4 EQc4:Indoor air quality assessment
posted by  Sue Bryant  on 

The reference guide states that "If multiple, discrete HVAC systems operate independently, the team may flush out portions of the building as work is completed in each area served by a given system

4
Technical Director
Centek Laboratories, LLC
LEEDuser Basic Member
13 thumbs up
Mon Dec 9, 2019, 3:51 pm

JUST Disclosure: Internal Communications

Pilot-Credits IPpc90:Social equity within the operations and maintenance staff
posted by  Allison Wilson  on 

Less a question and less specific to how to document IPpc90, my organization has just published its JUST disclosure and has embarked on an internal communications program to increase the impact thi

2
Integrated Design & LEED Specialist
SERA Architects
LEEDuser Expert
1361 thumbs up
Mon Dec 9, 2019, 3:01 pm