Forum » NC-2009 EAp1
Topic

Level of Participation by Enhanced CxA in Fundamental Cx Tasks

NC-2009 EAp1: Fundamental Commissioning of Building Energy Systems
posted by Annalise Reichert on Apr 9, 2015, 12:23 pm

We are currently working on a project where an independent third party was contracted to perform Enhanced Commissioning tasks, and a disinterested employee of the General Contractor performed...

Last reply: Scott Bowman, Apr 11, 2015, 2:47 pm

Sample LEED 2009 Basis of Design Document

NC-2009 EAp1: Fundamental Commissioning of Building Energy Systems
posted by Robert Shields on Apr 7, 2015, 11:34 am

I have a sample Basis of Design document that applies to LEED 2.2. Not sure if there are any differences in the requirements for the document required in LEED 2009. Would appreciate sample...

Last reply: Scott Bowman, Apr 7, 2015, 11:46 am

cxa requirements

NC-2009 EAp1: Fundamental Commissioning of Building Energy Systems
posted by andres ramirez on Nov 25, 2014, 2:30 pm

Hi I’m an arquitect and I just got the CPMP-...

Last reply: Scott Bowman, Mar 19, 2015, 6:16 pm

Domestic Hot Water System

NC-2009 EAp1: Fundamental Commissioning of Building Energy Systems
posted by Keerthi Ratnayake on Feb 26, 2015, 2:23 am

Is it a mandatory requirement to install a domestic hot water system in a LEED project?

Last reply: Keerthi Ratnayake, Feb 26, 2015, 12:11 pm

CxA Experience and energy systems

NC-2009 EAp1: Fundamental Commissioning of Building Energy Systems
posted by André Harms on Jul 14, 2014, 10:07 am

Hello, I would greatly appreciate some guidance on the below four queries:

Can a...

Last reply: Scott Bowman, Feb 11, 2015, 11:05 am

Who can be CxA?

NC-2009 EAp1: Fundamental Commissioning of Building Energy Systems
posted by Allan Vásquez on Dec 8, 2014, 6:01 pm

How do I know which projects are a similar managerial and technical complexity than the one I am working on? Let me explain me better, I work for the Costa Rica Government, where we have been...

Last reply: Allan Vásquez, Dec 11, 2014, 2:25 pm

Who can be CxA?

NC-2009 EAp1: Fundamental Commissioning of Building Energy Systems
posted by Allan Vásquez on Dec 9, 2014, 3:31 pm

Hi,
I’m looking for some help with the Commissioning Authority experience. The first question is:
How do I know which projects are similar managerial and technical complexity than the...

Medical gas system- part of fundamental commissioning?

NC-2009 EAp1: Fundamental Commissioning of Building Energy Systems
posted by Veronika Sundberg on Oct 13, 2014, 7:08 am

Hello, my qeustion is regarding our medical gas system and if it should be part of the fundamental commissionig for LEED?
We will undertake...

Last reply: Scott Bowman, Oct 13, 2014, 11:27 am

Do we need to Commission these systems?

NC-2009 EAp1: Fundamental Commissioning of Building Energy Systems
posted by Maya Karkour on Oct 8, 2014, 5:01 am

Dear Sirs,

I just want to double check if we need to commission, as part of the LEED PRerequisite / Credit, the following systems:
1) Pumps for water distribution, irrigation, sewage...

Last reply: Susan Walter, Oct 13, 2014, 8:56 am

On-site, third party owned solar

NC-2009 EAp1: Fundamental Commissioning of Building Energy Systems
posted by Nicholas Bristow on Sep 8, 2014, 9:58 am

Our project has an on-site, third party owned Solar PV system. The RECs have been sold to the local utility and replacement RECs per...

Last reply: Scott Bowman, Sep 8, 2014, 11:17 am