VOC TestingNC-2009 IEQc4.1: Low-emitting materials - adhesives and sealantsposted by Al Tibbs on Jan 6, 2010, 5:01 pm
I would not recommend a pid simply becauseit does not identify specific contaminants. I would use a Summa Canister for a more detailed and accurate analysis.... |
|
calculation of Cr 6.1 Stormwater design-Quantity ControlNC-2009 SSc6.1: Stormwater design - quantity controlposted by Gregory Hurst on Jan 5, 2010, 4:00 pm
Your calculations are correct. You will have to develop strategies to infiltrate, evapotranspire, or... Last reply: JP Rout, Jan 6, 2010, 4:03 am |
|
USGBC provides additional guidanceCI-2009 WEp1: Water Use Reductionposted by Shannon Gray on Dec 3, 2009, 12:08 pm
The USGBC just posted a new document providing additional guidance on WEp1 and WEc3. This document covers fixture groups, daily use calcs, dual flush flow rates, and autocontrol faucets. Link... Last reply: Devon Bertram, Jan 5, 2010, 3:33 pm |
|
The Naming of Options, and Knowing Which Applies to YouEBOM-2009 EAc1: Optimize Energy Efficiency Performanceposted by Jenny Carney on Jan 5, 2010, 3:08 pm
I just received an email with this question: "How do you know which calculator to use when trying to figure out the National Average. Your helpful hints indicate to use either calculator C or B.... |
|
LEED NC2.2 SSc4.3 & AGMBCGeneral forumsposted by Steve Loppnow on Jan 5, 2010, 10:15 am
It does appear as though the only option for SSc4.3 in the AGMBC is for alternative fueling stations. Although I don't know definitively why this is, I assume it is so that the appropriate number... |
|
Thread in IEQc3.2General forumsposted by Tristan Roberts on Jan 5, 2010, 9:35 am
For anyone following this thread, Peter has taken a slightly different approach, as covered in a new thread under CI IEQc3.2. |
|
Sample TemplateGeneral forumsposted by Dan Ackerstein on Jan 4, 2010, 5:48 pm
I think you're wise to seek a good look at the credit templates before making that decision, particularly if your project is an EBv2.0 project, as there is important information found in LEED... |
|
Irrigation of playing field in a soccer stadiumNC-2009 WEc1: Water Efficient Landscapingposted by WAGNER OLIVEIRA SILVA on Dec 11, 2009, 8:57 am
Concerning credit WEc1.1 and 1.2, there are some circumstances where it is unclear whether the water used for watering must be considered as irrigation water per intent of the credit or process... Last reply: Shannon Gray , Jan 4, 2010, 12:07 pm |
|
EBOM 2008 VS EBOM 2009EBOM-2009 EAp2: Minimum Energy Efficiency Performanceposted by Mary Davidge on Dec 23, 2009, 8:28 pm
Is there any real disadvantage to moving a project to LEED... Last reply: Jenny Carney, Dec 29, 2009, 12:10 pm |
|
Rock BallastingEBOM-2009 MRc9: Solid waste management - facility alterations and additionsposted by Chris Munn on Dec 28, 2009, 4:51 pm
If removing the rocks from a ballasted roof to coat the roof with an ENERGY STAR "cool roof", can these rock qualify for MR Cr9 as a material to be reused from a facility alteration? Last reply: Jenny Carney, Dec 28, 2009, 5:11 pm |