Post a question or comment
Filter by location
Forum
Topic
Replies
Recent

Entryway systems from undercover parking

NC-2009 IEQc5:Indoor Chemical and Pollutant Source Control
posted by  Ricardo Sá  on 

I'm working on a project that will have an entrance from an undercover parking below the building.

4
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Tue Jun 25, 2013, 3:27 pm

No open Space, just footprint.

CS-2009 SSc5.2:Site Development—Maximize Open Space
posted by  JOSE R. TAGLE  on 

“We have a project (North Tower) within the site of a project (South Tower), same owner, but each project would have their own certification.

3
Default Avatar
COMMISSIONING & LEED
AKF GROUP
LEEDuser Basic Member
2 thumbs up
Tue Jun 25, 2013, 1:56 pm

Re use of Concrete after slump cone test

NC-2009 MRc4:Recycled Content
posted by  Harish HA  on 

Can anybody suggest way of reuse of concrete generated from slump cone test of concrete and its debries to be reused with in the project site.

2
Default Avatar
LEEDuser Expert
472 thumbs up
Tue Jun 25, 2013, 8:23 am

Do I need to list all the products?

NC-2009 MRc4:Recycled Content
posted by  Jamie Abernethy  on 

I accidentally posted this in the Certified Wood section...If I take the default 45% of contract price for divisions 3-10 just in the concrete and steel my totals are 80% plus for recycled content

2
Default Avatar
LEEDuser Expert
472 thumbs up
Mon Jun 24, 2013, 9:00 pm

v4 Draft Rating System Documents

General forums
posted by  Michelle Rosenberger  on 

Morning gentlemen, Thanks for the debate presentation. A very good idea. FYI there's a lot more specific info provided above on the No side.

3
Mon Jun 24, 2013, 8:18 pm

Prescriptive vs permanent shading devices or roof overhangs

NC-2009 IEQc8.1:Daylight and Views—Daylight
posted by  Jorge Lopez de Obeso  on 

What is the reason for not being an option the prescriptive method in case a project have permanent shading devices or roof overhangs?

2
Energy Program Specialist
PA DMVA
LEEDuser Expert
626 thumbs up
Mon Jun 24, 2013, 2:47 pm

sealant applied to clearance between double glazing

NC-2009 IEQc4.1:Low-Emitting Materials—Adhesives and Sealants
posted by  Noriko Nagazumi  on 

Hi, Sealant which is applied to clearance between two glasses of double glazing window sash shall be evaluated for this credit compliance?

3
Mon Jun 24, 2013, 11:04 am

Submittal templates in metric Units

NC-2009 PIf1:Minimum Program Requirements
posted by  BABAR MEHMOOD  on 

We have a project in KSA and want to fill the online submittal templates regarding the Health care but we found the Imperial system for the templates, whereas metric system is follwed for all LEED

2
Sun Jun 23, 2013, 2:40 am

FSC COC Certification and Sub Contractors.

NC-2009 MRc7:Certified Wood
posted by  Leighton Dixon   on 

I am a General Contractor attempting to achieve MRc7 on an Office Building. In order to achieve the 50% we will need both the Wood Fencing and the Millwork to be FSC Certified.

3
LEED Program Manager
Sauer Incorporated
LEEDuser Basic Member
14 thumbs up
Sat Jun 22, 2013, 2:37 pm

Slate Porcelain Tiles

NC-2009 IEQc4.3:Low-Emitting Materials—Flooring Systems
posted by  Benjie Herrera  on 

Where do I classify the above tiles in the LEED online flooring materials listing ? Is it under Flooring: ceramic?

5
Fri Jun 21, 2013, 7:53 pm