Campus Walkway Lighting- Light Tresspass beyond LEED Boundary

Schools-2009 SSc8: Light Pollution Reduction
posted by Tim Hoeft on Nov 23, 2010, 10:46 am

Under Checklists:Pre-design on this site, it states:
"Campus projects can choose whether to comply with the requirements for the building site boundary or to meet the...

Who can be the CxA?

NC-2009 EAc3: Enhanced Commissioning
posted by Keith Amann on Nov 9, 2010, 12:06 pm

We have a situation where an owner wants to directly hire a sub-division of the civil engineering firm of record to perform enhanced...

Last reply: Chris Ladner, Nov 23, 2010, 9:07 am

exterior uplights under canopy

NC-2009 SSc8: Light Pollution Reduction
posted by gustavo goldman on Nov 23, 2010, 6:22 am

SSc8 includes a limitation in terms of the total initial designed fixture lumens emitted at an angle of 90 degrees or higher from nadir (for example, 2% for LZ2). Our project includes a number of...

Slag in concrete

NC-2009 MRc4: Recycled Content
posted by Summer Gorder on Aug 27, 2010, 12:44 am

How does slag contribute to LEED credit compliance?

Last reply: Keith Lindemulder, Nov 22, 2010, 6:20 pm

Multiple Extraction Locations

NC-2009 MRc5: Regional Materials
posted by Adolfo Silva on Feb 12, 2010, 3:24 pm

I work in Canada with the LEED Canada NC v1.0.
A steel stud supplier has provided multiple extraction locations and modes of transportation such as:
'ore came from Port, Quebec by...

Last reply: Keith Lindemulder, Nov 22, 2010, 5:33 pm

Wipe off mat

CI-2009 IEQc5: Indoor Chemical and Pollutant Source Control
posted by Alan Bernstein on Nov 18, 2010, 12:18 pm

I have space for a 10'x10' wipe off mat at the main exterior entrance of building, but the interior foyer is too small for a 10'x10' mat. The interior foyer has enough room for a 3'x3' mat. At...

Last reply: Tristan Roberts, Nov 22, 2010, 4:09 pm

Entryways into existing stairwells

EBOM-2009 IEQc3.5: Green cleaning - indoor chemical and pollutant source control
posted by Cara Weber on Nov 15, 2010, 9:08 am

An existing Hospital building has several 'main' entryways that are through stair towers. There is not anywhere near 10' available in these entryways which are located on landings (maybe 5'x8...

Last reply: Jason Franken, Nov 21, 2010, 4:28 pm

Floorscore

NC-2009 IEQc4.3: Low-emitting materials - flooring systems
posted by Nic Warner on Nov 18, 2010, 10:38 am

We are designing an athletic facility, and have been told by the manufacturer of the basketball court flooring, that "Solid...

Last reply: Lauren Sparandara, Nov 18, 2010, 3:20 pm

Ergonomic Design

General forums
posted by Simon Sue on Nov 18, 2010, 2:56 am

i have no experience in submitting Ergonomic design for ID credit but i get to know that there was a...

2009 CI IEQ Credit 5 Entryway System

General forums
posted by Alan Bernstein on Nov 17, 2010, 4:22 pm

Tristan Roberts Representative Vermont House of Representatives LEEDuser Expert 11470 thumbs up November 17, 2010- 5:56 pm Alan, can you post this question on our IEQc5 forum? Thanks.I think you'll also find some relevant posts there. Log in or register to post comments ...

Last reply: Tristan Roberts, Nov 17, 2010, 5:56 pm