Re-commisioningNC-2009 EAp1: Fundamental Commissioning of Building Energy Systemsposted by John Wood on Mar 9, 2016, 7:08 am
I am a PE who has been approached by a building owner with a request to have the building "re-commissioned." I have designed LEED projects before, and participated in the original... Last reply: John Wood, Mar 14, 2016, 2:15 pm |
|
Definition of one buildingNC-2009 PIf2: Project Summary Detailsposted by Cindy Quinn on Mar 15, 2016, 7:10 pmJon Clifford LEED-AP BD+C GREENSQUARE LEEDuser Expert 326 thumbs up March 15, 2016- 11:10 pm Cynthia—The definition of “one building” is on page 22 of the MPR Supplemental Guidance (http://www.usgbc.org/resources/leed-2009-mpr-supplemental-guidance-revis...). LEEDuser members may also see “Bird’s Eye View” tab on the MRP2 forum for more clarification (http://www.leeduser.com/credit/NC-2009/MPR2). If a project cannot qualify as one under these definitions, it can pursue a “Group” or a “Master Site” campus certification (http://www.leeduser.com/topic/new-leed-guidance-campuses-and-multiple-bu...) using the LEED Campus Guidance for Projects on a Shared... Last reply: Jon Clifford, Mar 23, 2016, 9:00 pm |
|
Solar EnergyNC-2009 EAc2: On-Site Renewable Energyposted by SAMY Chamy on Mar 16, 2016, 1:35 am
Dear Al:- Our project have 50 kWp Grid connected solar panel system with out battery back up. the project is individual and the solar panel is only for this factory alone the... Last reply: Marcus Sheffer, Mar 22, 2016, 11:15 am |
|
Baseline System 8NC-2009 EAp2: Minimum Energy Performanceposted by Vassil Vassilev on Mar 22, 2016, 10:43 am
Greetings, Last reply: Marcus Sheffer, Mar 22, 2016, 12:56 pm |
|
Percentage of Light Output/Wattage DimmedCI-2009 EAc1.2: Optimize energy performance - lighting controlsposted by Jordan Kirrane on Mar 22, 2016, 2:04 pmLEEDuser Expert 5903 thumbs up March 23, 2016- 11:23 am I answer questions here because it is in a public forum benefiting many. Sending me drawings crosses the line into my fee for service consulting... Last reply: Marcus Sheffer, Mar 23, 2016, 11:23 am |
|
n/aNC-2009 SSc4.3: Alternative transportation - low-emitting and fuel-efficient vehiclesposted by Anastasia Makarenko on Mar 31, 2016, 12:25 pm
Dear all, Last reply: Marilyn Specht, Apr 1, 2016, 11:03 am |
|
Outdoor airNC-v4 EAp2: Minimum Energy Performanceposted by Emmanuel Pauwels on Apr 4, 2016, 12:31 pm
In exception C in section G3.1.2.6 Ventilation, it states that 'If the minimum outdoor air intake flow in the proposed design is provided in excess of the amount required by the rating authority... Last reply: Marcus Sheffer, Jun 15, 2018, 11:52 am |
|
Cold ClimateNC-2009 SSc7.2: Heat island effect - roofposted by Erin Holdenried on Apr 5, 2016, 7:31 pm
Does anybody have experience using an alternate compliance path for a project in a cold climate? Last reply: Charles Nepps, Jun 6, 2016, 6:24 am |
|
Campus project- joint ESC plan and measuresNC-2009 SSp1: Construction Activity Pollution Preventionposted by Melinda Orova on Apr 14, 2016, 6:45 am
Hi, Last reply: Summer Minchew, Jan 28, 2019, 8:38 am |
|
Residential buildingLEED Rating System Selectionposted by Ana Paula Quiros on Apr 14, 2016, 1:34 pm
We have a residential building looking for certification. Which rating system would be more appropiate? New Construction or Core& Shell? Last reply: Tristan Roberts, Apr 15, 2016, 9:47 am |